Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.4 | 2.4 | 2.4 | 0 |
72W420 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-454/।।।(2)/22-39(एम0एल0ए0)/2017 दि0 07.01.2022
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
13.97
Resanction Cost :
13.97
Tentative Cost :
13.97
Exp. Upto Last Fy : 1.38
For CFY 2024-2025
Remaining : 12.59
Demand : 0.19
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 1.38
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 26 %
Up to Date : 26 %
Sanction on :
2 years 6 months ago
07 Jan 2022
Tentative Completion date:
8 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वेक्षण का कार्य पूर्ण। समरेखण गठित कर अनुमोदन हेतु इस कार्यालय के पत्रांक 624/18सी0 दि0 26.05.2022 द्वारा अधीक्षण अभियन्ता, 12वॉ वृत्त, लो0नि0वि0 पौडी को प्रेषित। अधीक्षण अभियन्ता, 12वॉ वृत्त, लो0नि0वि0 पौडी के पत्रांक 1934/1512 याता-12/22 दि0 10.06.2022 द्वारा समरेखण पर अनुमोदन प्राप्त। द्वितीय चरण स्टज-1 की स्वीकृति प्राप्त। अनुबन्ध गठित। पहाड कटान का कार्य प्रगति पर। -- as on 05-Feb-2024