Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 8 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 15 | 15 | 15 | 0 |
72W422 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-454/।।।(2)/22-39(एम0एल0ए0)/2017 दि0 07.01.2022
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
56.82
Resanction Cost :
56.82
Tentative Cost :
56.82
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 56.82
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Survey work done
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
2 years 6 months ago
07 Jan 2022
Tentative Completion date:
1 year 8 months from now
30 Mar 2026
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दि0 26.06.2022 को सर्वेक्षण का कार्य किया गया। भू-वैज्ञानिक द्वारा समरेखण का निरीक्षण किया गया। निरीक्षण आख्या अपेक्षित। ग्रामीणों द्वारा समरेखण में विवाद किया जा रहा है। पुनः दि0 01.02.2023 को सर्वेक्षण का कार्य पूर्ण। भू-वैज्ञानिक द्वारा सर्वेक्षण का निरीक्षण कर लिया गया है। निरीक्षण आख्या प्राप्त। भू-वैज्ञानिक द्वारा समरेखण में संशोधन किये जाने हेतु सुझाव दिये गये है। पुनः सर्वेक्षण कार्य किया जा रहा है। -- as on 03-Apr-2024
Physical Peramenters