Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
72W483 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 कम्प्यूटरजनित क्रमांक 1/119373/2023 ई पत्रावली संख्या-25463 दि0 03.05.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
4.50
Resanction Cost :
4.50
Tentative Cost :
4.50
Exp. Upto Last Fy : 0.09
For CFY 2024-2025
Remaining : 4.41
Demand : 1.00
Allotment : 0.00
Exp in CFY : 1.13
Total Up to Date Exp : 1.22
Survey work done
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
1 year 2 months ago
03 May 2023
Tentative Completion date:
1 year 8 months from now
30 Mar 2026
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दि0 18.12.2023 को सर्वेक्षण का कार्य पूर्ण। सहमति पत्र प्राप्त। भू-वैज्ञानिक द्वारा समरेखण का निरीक्षण किया जाना है। -- as on 03-Apr-2024
Physical Peramenters