Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 2.000 | 0.000 |
72W486 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 ई पत्रावली संख्या-41863 दि0 19.06.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
73.40
Resanction Cost :
73.40
Tentative Cost :
73.40
Exp. Upto Last Fy : 28.24
For CFY 2024-2025
Remaining : 45.16
Demand : 3.40
Allotment : 0.00
Exp in CFY : 18.53
Total Up to Date Exp : 46.78
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
1 year 4 weeks ago
19 Jun 2023
Tentative Completion date:
8 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित। पहाड़ कटान का कार्य प्रगति पर। -- as on 03-Apr-2024
Physical Peramenters