Work Profile Report [72W507]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0स0 ई पत्रावली संख्या-36291 दि0 15.09.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
50.93
Resanction Cost :
50.93
Tentative Cost :
50.93
Exp. Upto Last Fy :
31.64
For CFY 2024-2025
Remaining :
19.29
Demand :
19.29
Allotment :
19.29
Exp in CFY :
16.71
Total Up to Date Exp :
48.35
Work completed
Sanction on : 1 year 3 months ago
15 Sep 2023
Physical Progress:
At start of FY 2024-2025 :
90 %
Up to Date :
100 %
Tentative Completion date on : 5 months 3 weeks ago
30 Jun 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। वित्तीय दायित्व शेष। -- as on 29-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: