Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 0.000 | 1.5 | 1.500 | 0.000 |
72W507 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 ई पत्रावली संख्या-36291 दि0 15.09.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
50.93
Resanction Cost :
50.93
Tentative Cost :
50.93
Exp. Upto Last Fy : 31.64
For CFY 2024-2025
Remaining : 19.29
Demand : 19.29
Allotment : 0.00
Exp in CFY : 13.52
Total Up to Date Exp : 45.17
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
10 months 2 days ago
15 Sep 2023
Tentative Completion date:
2 weeks 3 days ago
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित। पहाड़ कटान का कार्य प्रगति पर। -- as on 03-Mar-2024
Physical Peramenters