Work Profile Report [72W516]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0स0 ई पत्रावली संख्या-36087 दि0 29.11.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
196.75
Resanction Cost :
196.75
Tentative Cost :
196.75
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
196.65
Demand :
196.65
Allotment :
63.31
Exp in CFY :
63.31
Total Up to Date Exp :
63.41
Construction Started
Sanction on : 1 year 3 weeks ago
29 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
15 %
Up to Date :
35 %
Tentative Completion date on : 3 months 4 days from now
30 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अनुबन्ध गठित। अतिरिक्त पहाड कटान एवं स्कपर एवं जी01, जी02 का पूर्ण। जी03 का कार्य प्रगति पर। -- as on 05-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: