Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 0.000 | 2.5 | 2.500 | 0.000 |
72W516 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 ई पत्रावली संख्या-36087 दि0 29.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
196.75
Resanction Cost :
196.75
Tentative Cost :
196.75
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 196.65
Demand : 196.75
Allotment : 100.00
Exp in CFY : 20.93
Total Up to Date Exp : 21.03
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 20 %
Sanction on :
7 months 2 weeks ago
29 Nov 2023
Tentative Completion date:
8 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित। अतिरिक्त पहाड कटान एवं स्कपर एवं जी01 का कार्य प्रगति पर। -- as on 28-Jun-2024
Physical Peramenters