Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 2.000 | 0.000 |
72W529 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रावली संख्या- 25463 दिनांक 01.12.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 368.32 Lacs
Resanction Cost : 368.32 Lacs
Exp. Upto Last Fy : 0.11 Lacs
For CFY 2024-2025
Remaining : 368.21 Lacs
Demand : 140.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.11 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 15 %
Sanction on :
5 months 2 weeks ago
01 Dec 2023
Tentative Completion date:
10 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित। अतिरिक्त पहाड कटान का कार्य प्रगति पर। -- as on 03-Apr-2024
Physical Peramenters