Work Profile Report [72W549]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई0 पत्रावली सं0- 36087 दिनांक 23.08.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
230.93
Resanction Cost :
230.93
Tentative Cost :
230.93
Exp. Upto Last Fy :
151.27
For CFY 2025-2026
Remaining :
79.66
Demand :
67.50
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
151.27
Construction Started
Sanction on : 8 months 3 weeks ago
23 Aug 2024
Physical Progress:
At start of FY 2025-2026 :
77 %
Up to Date :
95 %
Tentative Completion date on : 1 month 1 week from now
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पी0सी0 तक का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 05-May-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: