Work Profile Report [72W590]

राज्य योजना के अन्तर्गत जोगीमणी- सराईखेत मोटर मार्ग के किमी0 1 में सुधार एवं डामरीकरण का कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शासन की ई0पत्रावली सं0- 41863 दि0 15.10.2025

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

97.23

Resanction Cost :

97.23

Tentative Cost :

97.23

Exp. Upto Last Fy :

0.00

For CFY 2025-2026

Remaining :

97.23

Demand :

55.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

Work completed

Sanction on : 3 months 1 week ago

15 Oct 2025

Physical Progress:

At start of FY 2025-2026 :

0 %

Up to Date :

0 %

Tentative Completion date on : 6 months 3 weeks from now

18 Aug 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
1
1
1
-

Remark

view all

Overall Excess requirement 30 has been counted as tentative cost increased from 67.23 to 97.23 . -- as on 06-Jan-2026

Rating : 0

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: