Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 90 | 90 | 90 | 0 |
8W160 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 7075/।।।(2)/13-41 (प्रा0आ0)/2013 दि॰ 20.12.2013
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
84.24
Resanction Cost :
84.24
Tentative Cost :
84.24
Exp. Upto Last Fy : 27.14
For CFY 2024-2025
Remaining : 57.10
Demand : 35.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 27.14
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
10 years 6 months ago
20 Dec 2013
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
अपर सचिव, उत्तराखण्ड शासन के प0 360/एक्स-3-22/1(54)/ 2018 दि॰ 26.04.22 द्वारा 1.855 हे0 वनभूमि की विधिवत स्वीकृति प्राप्त।
1.32 किमी॰ मोटर मार्ग के द्वितीय चरण की स्वीकृति के सापेक्ष कार्य पूर्ण। सेतु के स्थल चयन एवं अवशेष मोटर मार्ग निर्माण की डी॰पी॰आर॰ गठन की कार्यवाही की जा रही हैै।
-- as on 30-Dec-2023
Physical Peramenters