Work Profile Report [8W172]

बछेर रोपा मोटर मार्ग से रोपा तल्ला तक मोटर मार्ग निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities
  • alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0सं0 333/।।।(2)/14-46 (प्रा0आ0)/2013 दि॰ 21.01.2014

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

17.73

Resanction Cost :

17.73

Tentative Cost :

6.66

Saving

11.07

Exp. Upto Last Fy :

0.66

For CFY 2025-2026

Remaining :

17.07

Demand :

5.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.66

Alignment Approved

Sanction on : 12 years 2 days ago

21 Jan 2014

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

10 %

Tentative Completion date on : 1 year 2 months from now

31 Mar 2027

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
1
1
1
-

Remark

view all

Overall Saving 11.07 has been recorded as expected cost of work reduced from 17.73 to 6.66 . कार्य के द्वितीय चरण की ई-डी0पी0आर0 गठित कर उच्चाधिकारियों को स्वीकृति हेतु प्रेषितं स्वीकृति के पश्चात द्वितीय चरण फेज-2 का कार्य पूर्ण होने के उपरांत ही नापभूमि प्रतिकर का भुगतान किया जाना सम्भव हो पायेगा। जिस कारण उक्त कार्य में बचत प्रदर्शित की गयी है। -- as on 30-Dec-2025

Rating : 4