Work Profile Report [8W224]

जनपद चमोली के विकासखण्ड दशोली में घुड़साल से सैकोट मोटर मार्ग का निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

  • Project Activities
  • alerts

    Documents

    Samples

Administrative Approval Detail : शा0 सं0 1971(1)/।।।(2)/13-52(प्रा0आ0) /2012 दिनांक 14.03.2013

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

103.16

Resanction Cost :

103.16

Tentative Cost :

103.16

Exp. Upto Last Fy :

2.15

For CFY 2025-2026

Remaining :

101.01

Demand :

2.70

Allotment :

1.08

Exp in CFY :

0.00

Total Up to Date Exp :

2.15

Alignment Approved

Sanction on : 12 years 3 weeks ago

14 Mar 2013

Physical Progress:

At start of FY 2025-2026 :

50 %

Up to Date :

50 %

Tentative Completion date on : 5 days 23 hours ago

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
8
8
8
-

Remark

view all

अधीक्षण अभियन्ता, सातवाॅ वृत्त, लो0नि0वि0, गोपेश्वर के प0 3730/53 याता-7/2023 दि0 24.09.2024 द्वारा 2.525 किमी0 का पुनरीक्षित संरेखण प्रस्ताव अनुमोदित। -- as on 08-Oct-2024

Rating : 50

Forest Case Pending At : 11: AIP Division

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: