Work Profile Report [8W28]
Tenders
alerts
Samples
Administrative Approval Detail : 3431/।।।-2/06-56 (प्रा॰आ॰)/06 दि॰ 22.12.06
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
493.95
Resanction Cost :
493.95
Tentative Cost :
493.95
Exp. Upto Last Fy :
3.08
For CFY 2025-2026
Remaining :
490.87
Demand :
220.00
Allotment :
60.35
Exp in CFY :
16.97
Total Up to Date Exp :
20.05
Construction Started
Sanction on : 18 years 6 months ago
22 Dec 2006
Physical Progress:
At start of FY 2025-2026 :
10 %
Up to Date :
10 %
Tentative Completion date on : 2 weeks 4 days ago
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 04-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: