Work Profile Report [8W294]
Tenders
alerts
Samples
Administrative Approval Detail : GO No 5298/III(2)/21-04(MLA)/2017 TC
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
135.35
Resanction Cost :
60.00
Tentative Cost :
60.00
Exp. Upto Last Fy :
2.56
For CFY 2025-2026
Remaining :
57.44
Demand :
15.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
2.56
Alignment Approved
Sanction on : 4 years 1 month ago
01 Nov 2021
Physical Progress:
At start of FY 2025-2026 :
5 %
Up to Date :
5 %
Tentative Completion date on : 8 months 2 weeks from now
31 Aug 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 75.35 has been recorded as expected cost of work reduced from 135.35 to 60.00 . -- as on 08-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2025 PWD Uttarakhand