Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 15.77 | 15.77 | 15.77 | 0 |
8W298 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : GO No- 1701/III(2)/22-04(M.L.A.)/2017 TC III
TS Amount (lakhs) : 396.13 Lacs
Financial Detail
Sanction Cost : 396.13 Lacs
Resanction Cost : 421.78 Lacs
Exp. Upto Last Fy : 264.55 Lacs
For CFY 2024-2025
Remaining : 157.23 Lacs
Demand : 140.06 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 264.55 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 72 %
Up to Date : 72 %
Sanction on :
2 years 1 month ago
29 Mar 2022
Tentative Completion date:
1 month 1 week from now
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Other Reason
वर्तमान में कार्यस्थल पर बर्फबारी के कारण कार्य प्रभावित हो रहा है व कार्य बन्द हो गया है | वर्णित क्षेत्र में बिजली, पानी एवं संचार व्यवस्था पूर्ण रूप से बाधित होने के कारण कार्य नहीं किया जा पा रहा है | उक्त कार्य अब इस वर्ष माह मार्च के अन्त में व मौसम अनुकूल होने पर ही पुनः प्रारम्भ किया जा सकेगा | -- as on 06-Mar-2024
Physical Peramenters