Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 |
8W466 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई-फाईल सं0 63879/लो0नि0वि0-2 दि0 06.12.2023
TS Amount (lakhs) : 389.99 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
389.99
Resanction Cost :
389.99
Tentative Cost :
389.99
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 389.89
Demand : 117.48
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
7 months 1 week ago
06 Dec 2023
Tentative Completion date:
1 year 1 month from now
10 Sep 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
ठेकेदार द्वारा स्थल पर mobilisation प्रारम्भ | -- as on 01-Jul-2024