Work Profile Report [8W55]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : 337/।।। (2)/09-43 (प्रा0आ0)/09 दि॰ 12.01.10
TS Amount (lakhs) : 330.74 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
330.74
Resanction Cost :
355.54
Tentative Cost :
326.82
Saving
28.72
Exp. Upto Last Fy :
315.32
For CFY 2025-2026
Remaining :
40.22
Demand :
4.90
Allotment :
0.97
Exp in CFY :
0.97
Total Up to Date Exp :
316.29
In Maintenance After Completion
Sanction on : 15 years 10 months ago
12 Mar 2010
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 years 9 months ago
21 Apr 2022
Actual Completion Date : 3 years 3 weeks ago
01 Jan 2023
Physical Linear Components
Remark
Overall Saving 28.72 has been recorded as expected cost of work reduced from 355.54 to 326.82 . -- as on 18-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2026 PWD Uttarakhand