Work Profile Report [9W17]
Tenders
Project Activities
Documents
Samples
Administrative Approval Detail : 3157/।।।(2)/ 06-71(प्रा0आ0)/ 06 दिं0 18.12.2006
TS Amount (lakhs) : 356 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
356.00
Resanction Cost :
356.00
Tentative Cost :
268.29
Saving
87.71
Exp. Upto Last Fy :
185.99
For CFY 2024-2025
Remaining :
170.01
Demand :
130.00
Allotment :
65.00
Exp in CFY :
64.98
Total Up to Date Exp :
250.97
Construction Started
Sanction on : 17 years 11 months ago
18 Dec 2006
Physical Progress:
At start of FY 2024-2025 :
90 %
Up to Date :
90 %
Tentative Completion date on : 1 month 3 weeks ago
30 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 87.71 has been recorded as expected cost of work reduced from 356 to 268.29 . -- as on 07-Nov-2024
Assets :