Work Profile Report [9W17]
Tenders
Project Activities
Documents
Samples
Administrative Approval Detail : 3157/।।।(2)/ 06-71(प्रा0आ0)/ 06 दिं0 18.12.2006
TS Amount (lakhs) : 356 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
356.00
Resanction Cost :
356.00
Tentative Cost :
268.29
Saving
87.71
Exp. Upto Last Fy :
185.99
For CFY 2024-2025
Remaining :
170.01
Demand :
130.00
Allotment :
68.09
Exp in CFY :
68.09
Total Up to Date Exp :
254.08
Work completed
Sanction on : 18 years 6 days ago
18 Dec 2006
Physical Progress:
At start of FY 2024-2025 :
90 %
Up to Date :
100 %
Tentative Completion date on : 3 months 6 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मार्ग मे 4.750 किमी0 का कार्य पूर्ण वर्तमान में बचत से 2.250 किमी0 का कार्य प्रगति पर है। -- as on 04-Dec-2024
Assets :