Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 6.000 | 0 | 2.000 | 2.000 |
9W337 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 3199/आर0आई0डी0एफ0-25(उत्तराखण्ड) 183 पी0सी0एस0 - 13.01.2020. 2019-2020 दिं0 21.01.2020
TS Amount (lakhs) : 367.04 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
405.93
Resanction Cost :
405.93
Tentative Cost :
367.04
Saving
38.89
Exp. Upto Last Fy : 300.44
For CFY 2024-2025
Remaining : 105.49
Demand : 66.60
Allotment : 40.00
Exp in CFY : 35.85
Total Up to Date Exp : 336.29
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 100 %
Sanction on :
4 years 5 months ago
21 Jan 2020
Tentative Completion date:
1 month 2 weeks ago
31 May 2024
Actual Completion Date:
1 month 2 weeks ago
31 May 2024
Remark
Bottelneck: no issue
कार्य की प्रशासकीय एवं वित्तीय स्वीकृति शा0सं0 1858/।।।(2)/ 16-56 एम0एल0ए0 2015 टी0सी0 दिं0 06.06.2016 द्वारा रू0 405.93 लाख मात्र की प्राप्त। जिसके सोपक्ष मुख्य अभियन्ता के पत्रांक 5806/02 याता0-ह0/ 2015 दिं0 19.09.2016 द्वारा रू0 367.04 लाख मात्र की प्राविधिक स्वीकृति निर्गत की गयी है। माह 12/2020 में नाबार्ड 25 में स्वीकृति। वर्तमान तक किया गया व्यय 77.02 (31.03.19 तक) + 24.98 (31.12.19 तक) कुल 102 लाख राज्य योजना के अन्तर्गत किया गया । किमी0 1 से 6 में पी0सी0 का कार्य पूर्ण। किमी0 1 व 2 में कुछ स्थानो पर पी0सी0 की मरम्मत का कार्य किया जाना। किमी0 3, 4, 5 व 6 मे अन्य विविध कार्य यथा नाली निर्माण, पैरापिट, दीवारो का कार्य पूर्ण। किमी0 1 व 2 मे पी0सी0 एवं अन्य कार्य अनुबन्ध गठित कर कार्य पूर्ण कर लिया गया है। -- as on 03-Jul-2024
Physical Peramenters