Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 0 |
9W415 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5082/III(2)2023-01(PE)/2023 Lok Niman Anubhag - 02 dt. 09-11-2023
TS Amount (lakhs) : 549.66 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
549.66
Resanction Cost :
549.66
Tentative Cost :
549.66
Exp. Upto Last Fy : 76.06
For CFY 2024-2025
Remaining : 473.60
Demand : 473.60
Allotment : 117.25
Exp in CFY : 4.58
Total Up to Date Exp : 80.64
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 30 %
Sanction on :
8 months 1 week ago
09 Nov 2023
Tentative Completion date:
1 month 2 weeks from now
05 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 12-Apr-2024