Administrative Approval Detail : जिलाधिकारी नैनीताल का पत्रांक 472/ जि0यो0 / स्वी0 / लो0नि0वि0 / 26-32/ 2025- 26 दिं0 22.07.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
8.00
Resanction Cost :
8.00
Tentative Cost :
8.00
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
8.00
Demand :
5.00
Allotment :
5.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
in Tendering Stage
Sanction on : 2 weeks 3 days ago
22 Jul 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
0 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
निविदा आमंत्रण की कार्यवाही प्रगति पर। -- as on 30-Jul-2025