4th Circle US Nagar [16 works]

Up to Date Expenditure : 20.20 Cr. Against Total Target : 94.16 Cr.
21%
20%

नाबार्ड वित्त पोषित आर0आई0डी0एफ0 योजना

3 works

6.45 Exp. / Target 33.05 Cr.

25%

चालू निर्माण कार्य-राज्य सैक्टर

3 works

13.47 Exp. / Target 54.75 Cr.

0%

पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

1 works

0.00 Exp. / Target 1.41 Cr.

0%

एस0सी0एस0पी0 योजना

2 works

0.00 Exp. / Target 0.62 Cr.

7%

टी0एस0पी0 योजना

7 works

0.28 Exp. / Target 4.33 Cr.

# Head Works Allotment Apr May Up to Last Month Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Total
T A T A T A % T A T T T T T T T T T T A %
1 NABARD 3 227.87 0 0 495.75 202.24 495.75 202.24 41 495.75 442.34 165.25 165.25 661 165.25 165.25 165.25 165.25 165.25 495.78 3305.03 644.58 20
2 State Sector 3 920 0 0 696.3 594.07 696.3 594.07 85 1413.7 752.9 240.35 240.35 961.42 240.35 240.35 240.35 240.35 240.35 721.11 5474.98 1346.97 25
3 Bridges State Sector 1 38 0 0 19 0 19 0 0 19 0 7.33 7.33 29.31 7.33 7.33 7.33 7.33 7.33 21.98 140.6 0 0
4 SCSP 2 0 0 0 0 0 0 0 18.41 0 3.09 3.09 12.37 3.09 3.09 3.09 3.09 3.09 9.28 61.69 0 0
6 TSP 7 0 0 0 54.45 0 54.45 0 0 110.55 28.4 19.17 19.17 76.68 19.17 19.17 19.17 19.17 19.17 57.51 433.38 28.4 7
Total 16 1185.87 0 0 1265.5 796.31 1265.5 796.31 63 2057.41 1223.64 435.19 435.19 1740.78 435.19 435.19 435.19 435.19 435.19 1305.66 9415.68 2019.95 21