CD Ramnagar [5 works]

Up to Date Expenditure : 3.92 Cr. Against Total Target : 12.33 Cr.
32%
10%

नाबार्ड वित्त पोषित आर0आई0डी0एफ0 योजना

1 works

0.07 Exp. / Target 0.73 Cr.

10%

चालू निर्माण कार्य-राज्य सैक्टर

1 works

0.47 Exp. / Target 4.74 Cr.

49%

पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

2 works

3.38 Exp. / Target 6.83 Cr.

0%

एस0सी0एस0पी0 योजना

1 works

0.00 Exp. / Target 0.02 Cr.

# Head Works Allotment Apr May Up to Last Month Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Total
T A T A T A % T A T T T T T T T T T T A %
1 NABARD 1 38.51 0 0 11.01 0 11.01 0 0 11.01 7.3 3.67 3.67 14.68 3.67 3.67 3.67 3.67 3.67 11.02 73.41 7.3 10
2 State Sector 1 50 0 0 26.4 26.76 26.4 26.76 101 53.6 20.19 28.16 28.16 112.66 28.16 28.16 28.16 28.16 28.16 84.53 474.31 46.95 10
3 Bridges State Sector 2 338.05 0 0 169 338.05 169 338.05 200 169 0 24.66 24.66 98.63 24.66 24.66 24.66 24.66 24.66 73.96 683.21 338.05 49
4 SCSP 1 0 0 0 0 0 0 0 0.51 0 0.08 0.08 0.34 0.08 0.08 0.08 0.08 0.08 0.28 1.69 0 0
Total 5 426.56 0 0 206.41 364.81 206.41 364.81 177 234.12 27.49 56.57 56.57 226.31 56.57 56.57 56.57 56.57 56.57 169.79 1232.62 392.3 32