PD Didihaat [21 works]

Up to Date Expenditure : 1.53 Cr. Against Total Target : 17.02 Cr.
9%
9%

नाबार्ड वित्त पोषित आर0आई0डी0एफ0 योजना

1 works

0.40 Exp. / Target 4.22 Cr.

11%

चालू निर्माण कार्य-राज्य सैक्टर

1 works

1.14 Exp. / Target 10.66 Cr.

0%

पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

11 works

0.00 Exp. / Target 0.55 Cr.

0%

एस0सी0एस0पी0 योजना

3 works

0.00 Exp. / Target 0.35 Cr.

0%

टी0एस0पी0 योजना

5 works

0.00 Exp. / Target 1.24 Cr.

# Head Works Allotment Apr May Up to Last Month Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Total
T A T A T A % T A T T T T T T T T T T A %
1 NABARD 1 212.42 0 0 63.32 24.85 63.32 24.85 39 63.32 14.91 21.11 21.11 84.43 21.11 21.11 21.11 21.11 21.11 63.32 422.16 39.76 9
2 State Sector 1 100 0 97.91 138.6 2.06 138.6 99.97 72 281.4 13.73 46.15 46.15 184.62 46.15 46.15 46.15 46.15 46.15 138.49 1066.16 113.7 11
3 Bridges State Sector 11 14.8 0 0 7.4 0 7.4 0 0 7.4 0 2.84 2.84 11.37 2.84 2.84 2.84 2.84 2.84 8.54 54.59 0 0
4 SCSP 3 0 0 0 15 0 15 0 0 0 0 1.44 1.44 5.76 1.44 1.44 1.44 1.44 1.44 4.33 35.17 0 0
6 TSP 5 0 0 0 11.55 0 11.55 0 0 23.45 0 6.33 6.33 25.3 6.33 6.33 6.33 6.33 6.33 18.94 123.55 0 0
Total 21 327.22 0 97.91 235.87 26.91 235.87 124.82 53 375.57 28.64 77.87 77.87 311.48 77.87 77.87 77.87 77.87 77.87 233.62 1701.63 153.46 9