CD Askote [10 works]

Up to Date Expenditure : 8.61 Cr. Against Total Target : 28.86 Cr.
30%
37%

नाबार्ड वित्त पोषित आर0आई0डी0एफ0 योजना

1 works

7.51 Exp. / Target 20.39 Cr.

13%

चालू निर्माण कार्य-राज्य सैक्टर

1 works

1.10 Exp. / Target 8.29 Cr.

0%

पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

8 works

0.00 Exp. / Target 0.17 Cr.

# Head Works Allotment Apr May Up to Last Month Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Total
T A T A T A % T A T T T T T T T T T T A %
1 NABARD 1 189.77 0 0 305.89 2.76 305.89 2.76 1 305.89 747.9 101.96 101.96 407.86 101.96 101.96 101.96 101.96 101.96 305.91 2039.27 750.66 37
2 State Sector 1 140 0 0 72.6 72.63 72.6 72.63 100 147.4 37.23 43.52 43.52 174.06 43.52 43.52 43.52 43.52 43.52 130.52 829.22 109.86 13
3 Bridges State Sector 8 5.5 0 0 2.62 0 2.62 0 0 2.62 0 0.87 0.87 1.74 1.74 1.74 0.87 0.87 0.87 2.63 17.44 0 0
Total 10 335.27 0 0 381.11 75.39 381.11 75.39 20 455.91 785.13 146.35 146.35 583.66 147.22 147.22 146.35 146.35 146.35 439.06 2885.93 860.52 30