CD Kashipur [3 works]

Up to Date Expenditure : 5.88 Cr. Against Total Target : 23.85 Cr.
25%
11%

नाबार्ड वित्त पोषित आर0आई0डी0एफ0 योजना

1 works

0.22 Exp. / Target 2.08 Cr.

27%

चालू निर्माण कार्य-राज्य सैक्टर

1 works

5.66 Exp. / Target 21.15 Cr.

0%

एस0सी0एस0पी0 योजना

1 works

0.00 Exp. / Target 0.61 Cr.

# Head Works Allotment Apr May Up to Last Month Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Total
T A T A T A % T A T T T T T T T T T T A %
1 NABARD 1 22.11 0 0 31.27 22.1 31.27 22.1 71 31.27 0 10.42 10.42 41.69 10.42 10.42 10.42 10.42 10.42 31.3 208.47 22.1 11
2 State Sector 1 190 0 0 310.2 162.6 310.2 162.6 52 629.8 402.95 83.95 83.95 335.8 83.95 83.95 83.95 83.95 83.95 251.86 2115.31 565.55 27
4 SCSP 1 0 0 0 0 0 0 0 18.41 0 3.07 3.07 12.27 3.07 3.07 3.07 3.07 3.07 9.18 61.35 0 0
Total 3 212.11 0 0 341.47 184.7 341.47 184.7 54 679.48 402.95 97.44 97.44 389.76 97.44 97.44 97.44 97.44 97.44 292.34 2385.13 587.65 25