PD Uttarkashi [3 works]

Up to Date Expenditure : 1.30 Cr. Against Total Target : 5.04 Cr.
26%
0%

नाबार्ड वित्त पोषित आर0आई0डी0एफ0 योजना

1 works

0.00 Exp. / Target 0.03 Cr.

26%

चालू निर्माण कार्य-राज्य सैक्टर

1 works

1.30 Exp. / Target 4.94 Cr.

0%

पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

1 works

0.00 Exp. / Target 0.07 Cr.

# Head Works Allotment Apr May Up to Last Month Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Total
T A T A T A % T A T T T T T T T T T T A %
1 NABARD 1 9.17 0 0 0.39 0 0.39 0 0 0.39 0 0.13 0.13 0.13 0.52 0.13 0.13 0.13 0.14 0.39 2.61 0 0
2 State Sector 1 70 0 0 49.5 64.28 49.5 64.28 130 100.5 65.72 24.59 24.59 98.37 24.59 24.59 24.59 24.59 24.59 73.79 494.29 130 26
3 Bridges State Sector 1 6.91 0 0 1.02 0 1.02 0 0 1.02 0 0.34 0.34 1.35 0.34 0.34 0.34 0.34 0.34 0.99 6.76 0 0
Total 3 86.08 0 0 50.91 64.28 50.91 64.28 126 101.91 65.72 25.06 25.06 99.85 25.45 25.06 25.06 25.06 25.07 75.17 503.66 130 26