PD Karnprayag [7 works]

Up to Date Expenditure : 0.88 Cr. Against Total Target : 5.73 Cr.
15%
0%

नाबार्ड वित्त पोषित आर0आई0डी0एफ0 योजना

1 works

0.00 Exp. / Target 0.00 Cr.

11%

चालू निर्माण कार्य-राज्य सैक्टर

1 works

0.43 Exp. / Target 4.04 Cr.

27%

एस0सी0एस0पी0 योजना

4 works

0.45 Exp. / Target 1.69 Cr.

0%

एन0पी0वी0 एवं भूमि प्रतिकर मद

1 works

0.00 Exp. / Target 0.00 Cr.

# Head Works Allotment Apr May Up to Last Month Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Total
T A T A T A % T A T T T T T T T T T T A %
1 NABARD 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
2 State Sector 1 80 0 0 39.6 4.4 39.6 4.4 11 80.4 38.57 20.29 20.29 81.17 20.29 20.29 20.29 20.29 20.29 60.88 404.08 42.97 11
4 SCSP 4 0 0 0 30 45.28 30 45.28 151 30 0 7.79 7.79 31.17 7.79 7.79 7.79 7.79 7.79 23.39 169.09 45.28 27
7 NPV 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Total 7 80 0 0 69.6 49.68 69.6 49.68 71 110.4 38.57 28.08 28.08 112.34 28.08 28.08 28.08 28.08 28.08 84.27 573.17 88.25 15