PD Rudraprayag [6 works]

Up to Date Expenditure : 4.53 Cr. Against Total Target : 34.99 Cr.
13%
12%

नाबार्ड वित्त पोषित आर0आई0डी0एफ0 योजना

1 works

0.41 Exp. / Target 3.40 Cr.

17%

चालू निर्माण कार्य-राज्य सैक्टर

1 works

1.95 Exp. / Target 11.47 Cr.

0%

पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

1 works

0.00 Exp. / Target 0.10 Cr.

0%

एस0सी0एस0पी0 योजना

1 works

0.00 Exp. / Target 0.08 Cr.

8%

केन्द्रीय सड़क अवसंरचना निधि (सी0आर0आई0एफ0)

1 works

1.68 Exp. / Target 19.93 Cr.

0%

एन0पी0वी0 एवं भूमि प्रतिकर मद

1 works

0.49 Exp. / Target 0.00 Cr.

# Head Works Allotment Apr May Up to Last Month Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Total
T A T A T A % T A T T T T T T T T T T A %
1 NABARD 1 80.77 0 0 51.06 1.27 51.06 1.27 2 51.06 39.3 17.02 17.02 68.08 17.02 17.02 17.02 17.02 17.02 51.06 340.4 40.57 12
2 State Sector 1 160 0 0 69.3 144.93 69.3 144.93 209 140.7 50.37 66.95 66.95 267.78 66.95 66.95 66.95 66.95 66.95 200.81 1147.24 195.3 17
3 Bridges State Sector 1 0 0 0 0 0 0 0 0 0 0.73 0.73 2.93 0.73 0.73 0.73 0.73 0.73 2.22 10.26 0 0
4 SCSP 1 0 0 0 0 0 0 0 2.51 0 0.42 0.42 1.67 0.42 0.42 0.42 0.42 0.42 1.24 8.36 0 0
5 CRIF 1 500 0 0 298.97 11.75 298.97 11.75 4 298.97 155.99 99.66 99.66 398.62 99.66 99.66 99.66 99.66 99.66 298.93 1993.11 167.74 8
7 NPV 1 0 0 0 0 0 0 0 0 49.18 0 0 0 0 0 0 0 0 0 0 49.18
Total 6 740.77 0 0 419.33 157.95 419.33 157.95 38 493.24 294.84 184.78 184.78 739.08 184.78 184.78 184.78 184.78 184.78 554.26 3499.37 452.79 13