PD New Tehri [8 works]
# | Head | Works | Allotment | Apr | May | Up to Last Month | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Jan | Feb | Mar | Total | |||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
T | A | T | A | T | A | % | T | A | T | T | T | T | T | T | T | T | T | T | A | % | ||||
1 | नाबार्ड वित्त पोषित आर0आई0डी0एफ0 योजना NABARD | 1 | 16.21 | 0 | 0 | 28.49 | 8.59 | 28.49 | 8.59 | 30 | 28.49 | 2.5 | 9.5 | 9.5 | 37.99 | 9.5 | 9.5 | 9.5 | 9.5 | 9.5 | 28.49 | 189.96 | 11.09 | 6 |
2 | चालू निर्माण कार्य-राज्य सैक्टर State Sector | 1 | 230 | 0 | 0 | 115.5 | 125.62 | 115.5 | 125.62 | 109 | 234.5 | 176.56 | 59.32 | 59.32 | 237.28 | 59.32 | 59.32 | 59.32 | 59.32 | 59.32 | 177.94 | 1180.46 | 302.18 | 26 |
3 | पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर Bridges State Sector | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | ||
4 | एस0सी0एस0पी0 योजना SCSP | 4 | 0 | 0 | 0 | 10.5 | 0 | 10.5 | 0 | 0 | 0 | 5.38 | 2.2 | 2.2 | 8.79 | 2.2 | 2.2 | 2.2 | 2.2 | 2.2 | 6.57 | 41.26 | 5.38 | 13 |
7 | एन0पी0वी0 एवं भूमि प्रतिकर मद NPV | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | ||
Total | 8 | 246.21 | 0 | 0 | 154.49 | 134.21 | 154.49 | 134.21 | 87 | 262.99 | 184.44 | 71.02 | 71.02 | 284.06 | 71.02 | 71.02 | 71.02 | 71.02 | 71.02 | 213 | 1411.68 | 318.65 | 23 |