TD Rishikesh [5 works]

Up to Date Expenditure : 20.98 Cr. Against Total Target : 64.95 Cr.
32%
9%

नाबार्ड वित्त पोषित आर0आई0डी0एफ0 योजना

1 works

0.66 Exp. / Target 7.15 Cr.

24%

चालू निर्माण कार्य-राज्य सैक्टर

1 works

8.98 Exp. / Target 37.56 Cr.

0%

पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

2 works

0.00 Exp. / Target 0.05 Cr.

56%

केन्द्रीय सड़क अवसंरचना निधि (सी0आर0आई0एफ0)

1 works

11.35 Exp. / Target 20.18 Cr.

# Head Works Allotment Apr May Up to Last Month Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Total
T A T A T A % T A T T T T T T T T T T A %
1 NABARD 1 54.23 0 0 107.32 18.01 107.32 18.01 17 107.32 47.86 35.77 35.77 143.09 35.77 35.77 35.77 35.77 35.77 107.34 715.46 65.87 9
2 State Sector 1 780 0 0 477.51 753.03 477.51 753.03 158 969.49 144.79 164.96 164.96 659.84 164.96 164.96 164.96 164.96 164.96 494.9 3756.46 897.82 24
3 Bridges State Sector 2 5.27 0 0 0.77 0 0.77 0 0 0.77 0 0.26 0.26 1.03 0.26 0.26 0.26 0.26 0.26 0.75 5.14 0 0
5 CRIF 1 526.44 0 0 302.69 0.2 302.69 0.2 0 302.69 1134.37 100.9 100.9 403.59 100.9 100.9 100.9 100.9 100.9 302.67 2017.94 1134.57 56
Total 5 1365.94 0 0 888.29 771.24 888.29 771.24 87 1380.27 1327.02 301.89 301.89 1207.55 301.89 301.89 301.89 301.89 301.89 905.66 6495 2098.26 32