CD Dehradun [10 works]

Up to Date Expenditure : 7.62 Cr. Against Total Target : 28.09 Cr.
27%
16%

नाबार्ड वित्त पोषित आर0आई0डी0एफ0 योजना

1 works

0.15 Exp. / Target 0.92 Cr.

30%

चालू निर्माण कार्य-राज्य सैक्टर

1 works

7.33 Exp. / Target 24.30 Cr.

5%

पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

8 works

0.15 Exp. / Target 2.87 Cr.

# Head Works Allotment Apr May Up to Last Month Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Total
T A T A T A % T A T T T T T T T T T T A %
1 NABARD 1 16.82 0 0 13.77 0 13.77 0 0 13.77 14.85 4.59 4.59 18.36 4.59 4.59 4.59 4.59 4.59 13.77 91.8 14.85 16
2 State Sector 1 460 0 0 151.8 459.92 151.8 459.92 303 308.2 272.87 140.71 140.71 562.86 140.71 140.71 140.71 140.71 140.71 422.18 2430.01 732.79 30
3 Bridges State Sector 8 95.25 0 0 42.2 11.24 42.2 11.24 27 42.2 3.36 14.47 14.47 57.87 14.47 14.47 14.47 14.47 14.47 43.4 286.96 14.6 5
Total 10 572.07 0 0 207.77 471.16 207.77 471.16 227 364.17 291.08 159.77 159.77 639.09 159.77 159.77 159.77 159.77 159.77 479.35 2808.77 762.24 27