TD Sahiya [67 works]

Up to Date Expenditure : 0.97 Cr. Against Total Target : 5.06 Cr.
19%
17%

नाबार्ड वित्त पोषित आर0आई0डी0एफ0 योजना

1 works

0.09 Exp. / Target 0.52 Cr.

24%

चालू निर्माण कार्य-राज्य सैक्टर

1 works

0.68 Exp. / Target 2.80 Cr.

6%

पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

16 works

0.01 Exp. / Target 0.22 Cr.

12%

टी0एस0पी0 योजना

49 works

0.19 Exp. / Target 1.52 Cr.

# Head Works Allotment Apr May Up to Last Month Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Total
T A T A T A % T A T T T T T T T T T T A %
1 NABARD 1 7.58 0 0 7.85 0 7.85 0 0 7.85 9.07 2.62 2.62 10.46 2.62 2.62 2.62 2.62 2.62 7.82 52.32 9.07 17
2 State Sector 1 50 0 0 27.06 20.18 27.06 20.18 75 54.94 48.29 14.13 14.13 56.54 14.13 14.13 14.13 14.13 14.13 42.44 279.89 68.47 24
3 Bridges State Sector 16 1.82 0 0 0.91 0 0.91 0 0 0.91 1.35 1.44 1.44 5.74 1.44 1.44 1.44 1.44 1.44 4.28 21.92 1.35 6
6 TSP 49 0 0 0 6.27 0 6.27 0 0 12.73 18.55 9.49 9.49 37.95 9.49 9.49 9.49 9.49 9.49 28.44 151.82 18.55 12
Total 67 59.4 0 0 42.09 20.18 42.09 20.18 48 76.43 77.26 27.68 27.68 110.69 27.68 27.68 27.68 27.68 27.68 82.98 505.95 97.44 19