CD Dugadda [29 works]

Up to Date Expenditure : 11.89 Cr. Against Total Target : 46.14 Cr.
26%
99%

नाबार्ड वित्त पोषित आर0आई0डी0एफ0 योजना

1 works

0.40 Exp. / Target 0.40 Cr.

25%

चालू निर्माण कार्य-राज्य सैक्टर

1 works

4.93 Exp. / Target 19.52 Cr.

25%

पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

20 works

6.47 Exp. / Target 25.58 Cr.

15%

एस0सी0एस0पी0 योजना

6 works

0.09 Exp. / Target 0.63 Cr.

0%

एन0पी0वी0 एवं भूमि प्रतिकर मद

1 works

0.00 Exp. / Target 0.00 Cr.

# Head Works Allotment Apr May Up to Last Month Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Total
T A T A T A % T A T T T T T T T T T T A %
1 NABARD 1 20.61 0 0 6.06 20.61 6.06 20.61 340 6.06 19.35 2.02 2.02 8.08 2.02 2.02 2.02 2.02 2.02 6.04 40.38 39.96 99
2 State Sector 1 400 0 45.12 166.65 190.63 166.65 235.75 141 338.35 257.26 103.32 103.32 413.3 103.32 103.32 103.32 103.32 103.33 309.99 1951.54 493.01 25
3 Bridges State Sector 20 900 0 0 390 199.44 390 199.44 51 390 447.26 127.03 127.03 508.11 127.03 127.03 127.03 127.03 127.03 381.05 2558.37 646.7 25
4 SCSP 6 0 0 0 10 0 10 0 0 15 9.38 2.73 2.73 10.92 2.73 2.73 2.73 2.73 2.73 8.19 63.22 9.38 15
7 NPV 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Total 29 1320.61 0 45.12 572.71 410.68 572.71 455.8 80 749.41 733.25 235.1 235.1 940.41 235.1 235.1 235.1 235.1 235.11 705.27 4613.51 1189.05 26