5650 - नि0ख0 पाबौ - Pauri
Total Damage Spots
Total Estimated Cost
Completed
Pending
EE Office: नि0ख0 पाबौ
District: Pauri
Segment ID: 162, EE Segment ID: 5650
Pics Count: 54
06-08-2025
1.Hill Side Cutting 2. Cross Drainage works( 2 scuppers) 3. Retaining Walls (RR1:6 and RR dry) 4. Breast Walls 5. Gabions 5. Plum Masonary 6. Pucca Drains
Remark: 125 m portion of road had been washed out due to land slide and heavy rain. Wing Wall of Bridge also damaged Work in Progress.
06-08-2025
Retainting Wall Damage
Remark: दीवार क्षतिग्रस्त
06-08-2025
Remark: स्कपर एवं दीवार क्षतिग्रस्त
06-08-2025
Remark: Scupper Damaged Due to Excess Water and Debris in Gadhera. Urgent Resconstruction deployed for opening Traffic
06-08-2025
Remark: Retaining Walls and Causeway surface Damaged. Urgent Reconstruction Work Deployed for opening Traffic.
06-08-2025
Remark: Scupper Washed out. Urgent Reconstruction work Deployed for opening Traffic
06-08-2025
Remark: दीवार क्षतिग्रस्त
07-08-2025
Remark: 35 m portion Washed out along With Scupper Back Hill Side Cutting Done partially For movement of Traffic. Further Work Required to be done Urgently Due To Regular Land Slides at Damaged portion
07-08-2025
Remark: दीवार क्षतिग्रस्त
07-08-2025
1.Hill Side Cutting 2. Retaining Walls (RR1:6 and RR dry) 3. Gabions 4. Plum Masonary
Remark: 3 Retaining Walls Damaged. Reconstruction in progress to allow Traffic movement
07-08-2025
1.Hill Side Cutting 2. Cross Drainage works( scupper/ Hume pipe) 3. Retaining Walls 4. Breast Walls 5. Gabions 5. Plum Masonary 6. Pucca Drains
Remark: 60 m Rockmass slide over along road caused Washout. Hill side Cutting being done.
07-08-2025
1.Hill Side Cutting 2. Cross Drainage works( scupper) 3. Retaining Walls(RR1:6 and RR Dry) 4. Breast Walls 5. Gabions 5. Plum Masonary 6. Pucca Drains
Remark: Two Washed out Portions, Bridge: Abutment, Protection wall and Wing walls Damaged, 4 Partial washout points. Back Cutting in Progress. Additional Protection Work required for opening traffic Back Cutting
10-08-2025
Remark: दीवार क्षतिग्रस्त
10-08-2025
RR Dry
Remark: Retaining Wall Damage
10-08-2025
Wall Damages
Remark: दीवार क्षतिग्रस्त
10-08-2025
Wall Damages
Remark: दीवार क्षतिग्रस्त
12-08-2025
Wall Damages
Remark: दीवार क्षतिग्रस्त
06-09-2025
1.Hill Side Cutting 2. Cross Drainage works( 2 scuppers) 3. Retaining Walls 4. Breast Walls 5. Gabions 5. Plum Masonary 6. Pucca Drains
Remark: 125 m portion of road had been washed out due to land slide and heavy rain. Work in Progress.
06-09-2025
1.Hill Side Cutting 2. Cross Drainage works( scupper) 3. Retaining Walls 4. Breast Walls 5. Gabions 5. Plum Masonary 6. Pucca Drains
Remark: Two Washed out Portions, Bridge: Abutment, Protection wall and Wing walls Damaged, 4 Partial washout points. Back Cutting in Progress. Additional Protection Work required for opening traffic Back Cutting
06-09-2025
1.Hill Side Cutting 2. Retaining Walls (RR1:6 and RR dry) 3. Gabions 4. Plum Masonary
Remark: 3 Retaining Walls Damaged. Reconstruction in progress to allow Traffic movement
06-09-2025
Remark: Retaining Walls and Causeway surface Damaged. Urgent Reconstruction Work Deployed for opening Traffic.
06-09-2025
Remark: Scupper Washed out. Urgent Reconstruction work Deployed for opening Traffic
06-09-2025
Remark: 35 m portion Washed out along With Scupper Back Hill Side Cutting Done partially For movement of Traffic. Further Work Required to be done Urgently Due To Regular Land Slides at Damaged portion
06-09-2025
Remark: Scupper Damaged Due to Excess Water and Debris in Gadhera. Urgent Resconstruction deployed for opening Traffic
07-09-2025
1.Hill Side Cutting 2. Cross Drainage works( scupper/ Hume pipe) 3. Retaining Walls 4. Breast Walls 5. Gabions 5. Plum Masonary 6. Pucca Drains
Remark: 60 m Rockmass slide over along road caused Washout. Hill side Cutting being done.
ID | Date | Location | Cost (₹) | Status | Yojana |
---|---|---|---|---|---|
1482 | 06-08-2025 | Ethur Market | 40.00 | Identified | Not Decided |
1478 | 06-08-2025 | Near Petrol PumP | 3.60 | Identified | Not Decided |
1505 | 06-08-2025 | Matiyalna | 9.00 | Identified | Not Decided |
1502 | 06-08-2025 | Bidala | 20.00 | Identified | Not Decided |
1489 | 06-08-2025 | Near Maso | 20.00 | Identified | Not Decided |
1492 | 06-08-2025 | Maso Village | 10.00 | Identified | Not Decided |
1500 | 06-08-2025 | Near Khirku | 4.00 | Identified | Not Decided |
1507 | 07-08-2025 | Near Maiyalna Pul | 28.00 | Identified | Not Decided |
1494 | 07-08-2025 | Near Maso | 10.00 | Identified | Not Decided |
1488 | 07-08-2025 | Near Maso | 30.00 | Identified | Not Decided |
1487 | 07-08-2025 | Ithur | 50.00 | Identified | Not Decided |
1485 | 07-08-2025 | Pingad Bridge | 70.00 | Identified | Not Decided |
1514 | 10-08-2025 | Chubattkhal Near | 14.50 | Identified | Not Decided |
1495 | 10-08-2025 | Near Khirku | 9.00 | Identified | Not Decided |
1512 | 10-08-2025 | Chubattakhal | 12.00 | Identified | Not Decided |
1510 | 10-08-2025 | Santudhar | 7.00 | Identified | Not Decided |
1511 | 12-08-2025 | Rigwadi | 8.00 | Identified | Not Decided |
1623 | 06-09-2025 | Ithur | 0.00 | Estimation Done | Not Decided |
1625 | 06-09-2025 | Near Pingad Bridge | 0.00 | Identified | Not Decided |
1627 | 06-09-2025 | Near Masaun | 0.00 | Identified | Not Decided |
1628 | 06-09-2025 | Masaun | 0.00 | Identified | Not Decided |
1631 | 06-09-2025 | Masaun | 0.00 | Identified | Not Decided |
1632 | 06-09-2025 | Matiyalna Pull | 0.00 | Identified | Not Decided |
1634 | 06-09-2025 | Bidala | 0.00 | Identified | Not Decided |
1624 | 07-09-2025 | Ithur after km 6 washout portion | 0.00 | Identified | Not Decided |