Infrastructure Damage Report : जाख अक्सोडा मोटर मार्ग

5042 - नि0ख0 पाबौ - Pauri

9

Total Damage Spots

₹ 29.23 Lakhs

Total Estimated Cost

1

Completed

8

Pending

Status Wise Distribution
Cost Analysis
जाख अक्सोडा मोटर मार्ग DivSegmentID:5042 Closure Report Closure Images

EE Office: नि0ख0 पाबौ

District: Pauri

Segment ID: 3489, EE Segment ID: 5042

Pics Count: 8

Damage Spots Details
Spot #1 - ID:1096 , जाख, अकसोडा, Chainage 5.00 - 5.049 , Damaged Length 0.049 KM

18-08-2025

Provisions (प्रावधानों की सूची)
  1. Excavation for Wing wall of Bridge
  2. RR Dry
  3. H.P.S filling
  4. plum

Remark: कार्य पूर्ण।

₹ 4.60 Lakh
Completed
Fund:Unknown
Spot #2 - ID:6834 , Jakh, Mailli markhola , chakisain, Chainage 1.150

22-07-2026

Provisions (प्रावधानों की सूची)
  1. Excavation work
  2. plum concrete work
  3. RR dry Retaining wall work
  4. Hps filling work

Remark: Road width decreased due to wall damage, urgent construction of Retaining wall is required

₹ 7.74 Lakh
Identified
Fund:Unknown
Spot #3 - ID:8730 , Jakh, aksoda, chakisain, Chainage 9.750

22-07-2026

Provisions (प्रावधानों की सूची)
  1. excavation
  2. plum concrete work
  3. dry
  4. hps
₹ 2.00 Lakh
Identified
Fund:Unknown
Spot #4 - ID:8731 , Jakh Aksoda , chakisain, Chainage 10.050

22-07-2026

Provisions (प्रावधानों की सूची)
  1. excavation
  2. plum concrete work
  3. dry
  4. hps
₹ 2.00 Lakh
Identified
Fund:Unknown
Spot #5 - ID:7297 , Jakh, Aksoda, chakisain, Chainage 1.990 - 2.000 , Damaged Length 0.01 KM

19-08-2026

Provisions (प्रावधानों की सूची)
  1. Excavation work
  2. gabions
  3. RR dry Retaining wall work
  4. Hps filling work

Remark: Requirement of retaining wall

₹ 4.00 Lakh
Estimation Done
Fund:Unknown
Spot #6 - ID:7298 , Jakh Aksoda , chakisain, Chainage 1.980

19-08-2026

Provisions (प्रावधानों की सूची)
  1. Excavation work
  2. RR dry Retaining wall work
  3. Hps filling work

Remark: Very necessary to construct a retaining wall because the road width decreases day by day

₹ 2.56 Lakh
Identified
Fund:Unknown
Spot #7 - ID:8732 , Jakh ,malli markhola, chakisain, Chainage 0.990

19-08-2026

Provisions (प्रावधानों की सूची)
  1. Excavation
  2. plum concrete work
  3. RR dry
  4. HPS filling
₹ 2.56 Lakh
Identified
Fund:Unknown
Spot #8 - ID:8795 , Jakh, mailli markhola, danda markhola, chakisain, Chainage 2.650

05-10-2026

Provisions (प्रावधानों की सूची)
  1. Excavation
  2. plum concrete work
  3. gabions
  4. HPS filling
₹ 1.79 Lakh
Identified
Fund:Unknown
Spot #9 - ID:8796 , Jakh, mailli markhola, danda markhola, chakisain, Chainage 4.460

05-10-2026

Provisions (प्रावधानों की सूची)
  1. Excavation
  2. plum concrete work
  3. gabions
  4. HPS filling
₹ 1.98 Lakh
Identified
Fund:Unknown

All Damage Spots

ID Date Location Cost (₹ Lakh) Chainages Status Yojana
1096 18-08-2025 जाख, अकसोडा 4.60 5.00 to 5.049 0.049 Completed SDRF
6834 22-07-2026 Jakh, Mailli markhola , chakisain 7.74 Identified Not Decided
8730 22-07-2026 Jakh, aksoda, chakisain 2.00 Identified Not Decided
8731 22-07-2026 Jakh Aksoda , chakisain 2.00 Identified Not Decided
7297 19-08-2026 Jakh, Aksoda, chakisain 4.00 1.990 to 2.000 0.01 Estimation Done SDMF
7298 19-08-2026 Jakh Aksoda , chakisain 2.56 Identified Not Decided
8732 19-08-2026 Jakh ,malli markhola, chakisain 2.56 Identified Not Decided
8795 05-10-2026 Jakh, mailli markhola, danda markhola, chakisain 1.79 Identified Not Decided
8796 05-10-2026 Jakh, mailli markhola, danda markhola, chakisain 1.98 Identified Not Decided