Balance Cost at Start of Fy : 1807.52 Lacs. New Works Sanctioned in This Fy: 39 No of Rs 280.6 Lacs

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2024 0 0
May, 2024 43.5 45.75
Jun, 2024 135.53 176.77
Jul, 2024 192.73 211.99
Aug, 2024 228.96 212.49
Sep, 2024 285.96 212.49
Oct, 2024 309.34 212.49
Nov, 2024 313.23 212.49
Dec, 2024 313.23 212.49
Jan, 2025 313.23 212.49
Feb, 2025 313.23 212.49
Mar, 2025 313.23 212.49