SRMD

Balance Cost at Start of Fy : 446.85 Lacs. New Works Sanctioned in This Fy: 8 No of Rs 148.35 Lacs

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2024 0 16.14
May, 2024 30 46.14
Jun, 2024 66.39 46.14
Jul, 2024 66.39 58.27
Aug, 2024 102.39 58.34
Sep, 2024 130.89 75.53
Oct, 2024 175.69 75.53
Nov, 2024 183.69 75.53
Dec, 2024 194.69 75.53
Jan, 2025 209.69 75.53
Feb, 2025 252.69 75.53
Mar, 2025 307.32 75.53

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 0 0
May, 2024 0 0 0
Jun, 2024 0 0 0
Jul, 2024 0 0 0
Aug, 2024 0 0 0
Sep, 2024 0 0 0
Oct, 2024 0 0 0
Nov, 2024 0 0 0
Dec, 2024 0 0 0
Jan, 2025 0 0 0
Feb, 2025 0 0 0
Mar, 2025 0 0 0

Instant Demand

Cummulative Demand
Up to Sep-2024

0 Lacs