SRMD

Balance Cost at Start of Fy : 1376.60 Lacs. New Works Sanctioned in This Fy: 2 No of Rs 57.01 Lacs

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2024 0 0
May, 2024 0 4.86
Jun, 2024 0 32.75
Jul, 2024 100 139.07
Aug, 2024 150 179.29
Sep, 2024 150 179.29
Oct, 2024 204 410.52
Nov, 2024 239 412.15
Dec, 2024 249 412.15
Jan, 2025 249 412.15
Feb, 2025 249 412.15
Mar, 2025 297.51 412.15

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 0 0
May, 2024 0 0 0
Jun, 2024 0 0 0
Jul, 2024 0 0 0
Aug, 2024 0 0 0
Sep, 2024 0 0 0
Oct, 2024 0 0 0
Nov, 2024 0 0 0
Dec, 2024 0 12 0
Jan, 2025 0 20 0
Feb, 2025 0 28 0
Mar, 2025 0 28 0

Instant Demand

Cummulative Demand
Up to Nov-2024

0 Lacs

History (in Reverse Order)

01 Apr 2024 0.00

Allotment

Cummulative Allotment

0 Lacs

History (in Reverse Order)

01 Apr 2024 0.00

IFMS Payments