SRMD

Balance Cost at Start of Fy : 4899.62 Lacs. New Works Sanctioned in This Fy: 1 No of Rs 481 Lacs

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2024 100 126.47
May, 2024 376.68 329.55
Jun, 2024 741.08 519.7
Jul, 2024 935.17 530.88
Aug, 2024 1104.09 1000.51
Sep, 2024 1439.1 1000.51
Oct, 2024 1747.32 1000.51
Nov, 2024 2153.32 1000.51
Dec, 2024 2525.21 1000.51
Jan, 2025 2815.21 1000.51
Feb, 2025 3155.21 1000.51
Mar, 2025 3933.05 1000.51

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 0 0
May, 2024 0 0 0
Jun, 2024 0 0 0
Jul, 2024 0 0 0
Aug, 2024 0 0 0
Sep, 2024 0 0 0
Oct, 2024 0 0 0
Nov, 2024 0 0 0
Dec, 2024 0 0 0
Jan, 2025 0 0 0
Feb, 2025 0 0 0
Mar, 2025 0 0 0

Instant Demand

Cummulative Demand
Up to Sep-2024

0 Lacs

History (in Reverse Order)

01 Apr 2024 0.00

Allotment

Cummulative Allotment

0 Lacs

History (in Reverse Order)

01 Apr 2024 0.00

IFMS Payments