Refresh data
on Monday, September 18th 2023, 6:30:00 pm
Work Sanctioned
जिला योजना वर्ष 2023-24 के अन्तर्गत तल्ला रामगढ़ रातीघाट मोटर मार्ग के कि0मी0 1 है0मी0 4 से 6 में ग्राम पाली एवं नैकाना को जोड़ने हेतु 24 मी0 स्पान स्टील गर्डर पुल स्थापित करने का कार्य।
on Thursday, November 30th 2023, 10:57:47 am
Technical Sanction
of ₹ 31.92 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 2638/36 सी0 दिं0 30.11.2023
on Tuesday, December 12th 2023, 6:42:48 am
PWD UttarakahndPhoto (ID 31901) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Briddle bridge foundation excavation work
on Tuesday, December 12th 2023, 6:47:28 am
PWD UttarakahndPhoto (ID 31902) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Foundation
on Tuesday, December 12th 2023, 6:49:08 am
PWD UttarakahndPhoto (ID 31903) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Foundation excavation
on Tuesday, December 12th 2023, 6:50:41 am
PWD UttarakahndPhoto (ID 31904) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Excavation
on Tuesday, December 12th 2023, 6:53:51 am
PWD UttarakahndPhoto (ID 31905) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Foundation work
on Wednesday, December 13th 2023, 7:39:29 am
PWD UttarakahndPhoto (ID 32023) from Site Received
Uploader : Prakash Chandra Pant, Assistant Engineer Civil ,CD Nainital
Landmark : Naikana bridge Talla Ramgarh
Remark : Foundation work
on Wednesday, December 13th 2023, 7:44:04 am
PWD UttarakahndPhoto (ID 32024) from Site Received
Uploader : Prakash Chandra Pant, Assistant Engineer Civil ,CD Nainital
Landmark : Naikana bridge Talla Ramgarh
Remark : Dewatering
on Sunday, December 17th 2023, 9:30:32 am
PWD UttarakahndPhoto (ID 32487) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Footing
on Sunday, December 17th 2023, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time
on Tuesday, December 19th 2023, 8:37:06 am
PWD UttarakahndPhoto (ID 32883) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Abutment
on Tuesday, December 19th 2023, 8:38:01 am
PWD UttarakahndPhoto (ID 32884) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Abutment
on Tuesday, December 19th 2023, 8:44:58 am
PWD UttarakahndPhoto (ID 32887) from Site Received
Uploader : Prakash Chandra Pant, Assistant Engineer Civil ,CD Nainital
Landmark : Km 1
Remark : Work in progress
on Saturday, December 23rd 2023, 6:59:36 am
PWD UttarakahndPhoto (ID 33458) from Site Received
Uploader : Prakash Chandra Pant, Assistant Engineer Civil ,CD Nainital
Landmark : Talla Ramgarh
Remark : Work in progress
on Wednesday, December 27th 2023, 11:21:20 am
PWD UttarakahndPhoto (ID 33631) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Abutment
on Wednesday, December 27th 2023, 11:34:53 am
PWD UttarakahndPhoto (ID 33636) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Abutment
on Friday, December 29th 2023, 10:45:40 am
PWD UttarakahndPhoto (ID 33882) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Back Filling Approch of abutment
on Thursday, January 4th 2024, 7:18:57 am
PWD UttarakahndPhoto (ID 34229) from Site Received
Uploader : Prakash Chandra Pant, Assistant Engineer Civil ,CD Nainital
Landmark : Km 8
Remark : Work in progress
on Thursday, January 4th 2024, 8:00:07 am
PWD UttarakahndPhoto (ID 34239) from Site Received
Uploader : Prakash Chandra Pant, Assistant Engineer Civil ,CD Nainital
Landmark : Naikana bridge
Remark : Work in progress
on Tuesday, January 9th 2024, 7:36:12 am
PWD UttarakahndPhoto (ID 34499) from Site Received
Uploader : Prakash Chandra Pant, Assistant Engineer Civil ,CD Nainital
Landmark : Naikana bridge
Remark : Work in progress
on Tuesday, January 9th 2024, 7:54:41 am
PWD UttarakahndPhoto (ID 34502) from Site Received
Uploader : Prakash Chandra Pant, Assistant Engineer Civil ,CD Nainital
Landmark : Naikana bridge
Remark : Work in progress
on Friday, January 12th 2024, 6:33:14 am
PWD UttarakahndPhoto (ID 34767) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Abumtement No 2
on Friday, January 12th 2024, 6:35:32 am
PWD UttarakahndPhoto (ID 34769) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : RCC Band
on Friday, January 12th 2024, 7:52:25 am
PWD UttarakahndPhoto (ID 34779) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Abutment
on Friday, January 12th 2024, 9:22:31 am
PWD UttarakahndPhoto (ID 34804) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Abutment RCC Band
on Thursday, January 18th 2024, 7:58:40 am
PWD UttarakahndPhoto (ID 34951) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Abutment RCC band Reinforcement cutting
on Saturday, January 20th 2024, 7:28:01 am
PWD UttarakahndPhoto (ID 35055) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Abutment
on Thursday, January 25th 2024, 7:37:23 am
PWD UttarakahndPhoto (ID 35199) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Top RCC Band Casting for abutment
on Thursday, January 25th 2024, 7:51:19 am
PWD UttarakahndPhoto (ID 35205) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Top band Casting
on Thursday, January 25th 2024, 8:20:44 am
PWD UttarakahndPhoto (ID 35209) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Abutment 2 top RCC band casting
on Thursday, January 25th 2024, 8:43:55 am
PWD UttarakahndPhoto (ID 35212) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Top Bed block
on Saturday, January 27th 2024, 8:01:04 am
PWD UttarakahndPhoto (ID 35278) from Site Received
Uploader : Prakash Chandra Pant, Assistant Engineer Civil ,CD Nainital
Landmark : Naikana bridge
Remark : Work in progress
on Monday, January 29th 2024, 6:30:00 pm
20.16%
Financial Progress
1st Expenditure
of ₹ 643653 (6.44 Lacs ) done.
Cummulative ₹ 6.44Lacs ( against 31.92Lacs )
on Saturday, February 17th 2024, 4:58:09 am
PWD UttarakahndPhoto (ID 35987) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Abutment protection work
on Monday, February 26th 2024, 6:46:25 am
PWD UttarakahndPhoto (ID 36283) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Bridge erection
on Monday, February 26th 2024, 7:24:48 am
PWD UttarakahndPhoto (ID 36285) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Bridge erection
on Wednesday, February 28th 2024, 6:30:00 pm
43.80%
Financial Progress
2nd Expenditure
of ₹ 754519 (7.55 Lacs ) done.
Cummulative ₹ 13.98Lacs ( against 31.92Lacs )
on Thursday, February 29th 2024, 7:26:00 am
PWD UttarakahndPhoto (ID 36415) from Site Received
Uploader : Sanjay Kumar Pandey, Executive Engineer Civil ,PD Bageshwar
Landmark : Bridge erection
Remark : Work progress
on Thursday, February 29th 2024, 8:21:58 am
PWD UttarakahndPhoto (ID 36414) from Site Received
Uploader : Prakash Chandra Pant, Assistant Engineer Civil ,CD Nainital
Landmark : Naikana bridge
Remark : Work in progress
on Friday, March 1st 2024, 8:02:24 am
PWD UttarakahndPhoto (ID 36469) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Bridge
on Tuesday, March 5th 2024, 5:46:36 am
PWD UttarakahndPhoto (ID 36552) from Site Received
Uploader : Prakash Chandra Pant, Assistant Engineer Civil ,CD Nainital
Landmark : Naikana bridge
Remark : Work in progress
on Tuesday, March 5th 2024, 5:46:40 am
PWD UttarakahndPhoto (ID 36553) from Site Received
Uploader : Sanjay Kumar Pandey, Executive Engineer Civil ,PD Bageshwar
Landmark : Bridge work
Remark : Erection work going
on Saturday, March 9th 2024, 7:44:04 am
PWD UttarakahndPhoto (ID 36620) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Bridel bridge
on Saturday, March 9th 2024, 7:45:22 am
PWD UttarakahndPhoto (ID 36621) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Bridel Bridge erection
on Wednesday, March 13th 2024, 9:09:01 am
PWD UttarakahndPhoto (ID 36708) from Site Received
Uploader : Prakash Chandra Pant, Assistant Engineer Civil ,CD Nainital
Landmark : Naikana bridge
Remark : Work in progress
on Wednesday, March 13th 2024, 9:10:55 am
PWD UttarakahndPhoto (ID 36709) from Site Received
Uploader : Prakash Chandra Pant, Assistant Engineer Civil ,CD Nainital
Landmark : Naikana bridge
Remark : Work in progress
on Friday, March 15th 2024, 6:38:19 am
PWD UttarakahndPhoto (ID 36783) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Work in progress
on Friday, March 15th 2024, 8:30:42 am
PWD UttarakahndPhoto (ID 36792) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Measurements
on Monday, April 15th 2024, 6:30:00 pm
70.68%
Financial Progress
3rd Expenditure
of ₹ 857917 (8.58 Lacs ) done.
Cummulative ₹ 22.56Lacs ( against 31.92Lacs )
on Thursday, May 16th 2024, 9:47:22 am
PWD UttarakahndPhoto (ID 38942) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Shuttering for slab
on Thursday, May 16th 2024, 9:48:18 am
PWD UttarakahndPhoto (ID 38944) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Stairs for bridle bridge
on Saturday, May 18th 2024, 5:56:49 am
PWD UttarakahndPhoto (ID 39190) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Reinforcement slab
on Saturday, May 18th 2024, 5:58:37 am
PWD UttarakahndPhoto (ID 39191) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : RCC
on Saturday, May 18th 2024, 6:13:12 am
PWD UttarakahndPhoto (ID 39196) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : RCC
on Saturday, May 18th 2024, 6:33:12 am
PWD UttarakahndPhoto (ID 39201) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : RCC For Slab
on Saturday, May 18th 2024, 7:02:18 am
PWD UttarakahndPhoto (ID 39212) from Site Received
Uploader : Vijay Singh, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : RCC work
on Tuesday, May 21st 2024, 7:30:39 am
PWD UttarakahndPhoto (ID 39471) from Site Received
Uploader : Prakash Chandra Pant, Assistant Engineer Civil ,CD Nainital
Landmark : Naikana bridge
Remark : Work is nearly over
on Tuesday, July 2nd 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, September 12th 2024, 6:30:00 pm
99.15%
Financial Progress
4th Expenditure
of ₹ 908863 (9.09 Lacs ) done.
Cummulative ₹ 31.65Lacs ( against 31.92Lacs )