Work Sanctioned
सड़क सुरक्षा मद के अन्तर्गत रामनगर भण्डारपानी अमगड़ी बोहराकोट ओखलढूॅगा तल्ली सेठी बेतालघाट रतौड़ा भुजान विशालकोट जैना रीची बिल्लेख (राज्य मार्ग सं0-71) मोटर मार्ग के कि0मी0 45 से 69 के मध्य प्रस्तावित सड़क सुरक्षा कार्य।
on Friday, March 28th 2025, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 1st time
on Monday, May 26th 2025, 6:30:00 pm
95%
Physical Progress
Physical Progress Reported at 2nd time
on Friday, June 27th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 3rd time
on Thursday, July 3rd 2025, 6:30:00 pm
59.13%
Financial Progress
1st Expenditure
of ₹ 40000000 (400.00 Lacs ) done.
Cummulative ₹ 400.00Lacs ( against 676.44Lacs )