Work Sanctioned
राज्य योजना के अन्तर्गत जनपद नैनीताल के विधानसभा क्षेत्र रामनगर के ग्राम शिवलालपुर पाण्डे, रियूनियां में रेलवे क्रासिंग से दक्षिण दिशा की ओर गाॅव को जाने वाले मार्ग का नव निर्माण कार्य।

2 years ago

on Monday, September 18th 2023, 11:01:20 am

Technical Sanction
of ₹ 59.89 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS Vide 398/ EE Date 18/09/2023

2 years ago

on Monday, February 12th 2024, 6:30:00 pm
45%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Sunday, February 25th 2024, 6:30:00 pm
0.18%
Financial Progress

1st Expenditure
of ₹ 10795 (0.11 Lacs ) done.
Cummulative ₹ 0.11Lacs ( against 59.89Lacs )

2 years ago

on Friday, March 1st 2024, 6:30:00 pm
42.49%
Financial Progress

2nd Expenditure
of ₹ 2533705 (25.34 Lacs ) done.
Cummulative ₹ 25.45Lacs ( against 59.89Lacs )

a year ago

on Thursday, March 21st 2024, 6:30:00 pm
58.98%
Financial Progress

3rd Expenditure
of ₹ 987660 (9.88 Lacs ) done.
Cummulative ₹ 35.32Lacs ( against 59.89Lacs )

a year ago

on Friday, March 22nd 2024, 6:30:00 pm
60.93%
Financial Progress

4th Expenditure
of ₹ 116900 (1.17 Lacs ) done.
Cummulative ₹ 36.49Lacs ( against 59.89Lacs )

a year ago

on Friday, May 3rd 2024, 6:30:00 pm
65%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Thursday, September 19th 2024, 6:30:00 pm
70.99%
Financial Progress

5th Expenditure
of ₹ 602265 (6.02 Lacs ) done.
Cummulative ₹ 42.51Lacs ( against 59.89Lacs )

a year ago

on Thursday, October 3rd 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 3rd time

a year ago

on Sunday, October 27th 2024, 6:30:00 pm
71.44%
Financial Progress

6th Expenditure
of ₹ 27004 (0.27 Lacs ) done.
Cummulative ₹ 42.78Lacs ( against 59.89Lacs )

10 months ago

on Monday, December 2nd 2024, 6:30:00 pm
85.98%
Financial Progress

7th Expenditure
of ₹ 871080 (8.71 Lacs ) done.
Cummulative ₹ 51.49Lacs ( against 59.89Lacs )

9 months ago

on Wednesday, December 11th 2024, 6:30:00 pm
86.20%
Financial Progress

8th Expenditure
of ₹ 12980 (0.13 Lacs ) done.
Cummulative ₹ 51.62Lacs ( against 59.89Lacs )

9 months ago

on Wednesday, December 11th 2024, 6:30:00 pm
86.50%
Financial Progress

9th Expenditure
of ₹ 17818 (0.18 Lacs ) done.
Cummulative ₹ 51.80Lacs ( against 59.89Lacs )

9 months ago

on Tuesday, December 31st 2024, 6:30:00 pm
86.99%
Financial Progress

10th Expenditure
of ₹ 29618 (0.30 Lacs ) done.
Cummulative ₹ 52.10Lacs ( against 59.89Lacs )