2 years ago

on Wednesday, March 6th 2024, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री घोषणा संख्या-607/2019 के अन्तर्गत वित्तीय वर्ष 2023-24 में जनपद नैनीताल के विधान सभा क्षेत्र रामनगर में हाथीडंगर कानिया नाला पर 30 मी0 स्पान सेतु का निर्माण। (विस्तृत आगणन)

a year ago

on Saturday, August 10th 2024, 10:47:00 am
<span class="4">Picture Id:51781</span>
PWD Uttarakahnd
Photo (ID 51781) from Site Received
Uploader : Uma Shanker Kukreti, Additional Assistant Engineer Civil ,CD Ramnagar
Landmark : Hathidangar kaniya nala
Remark : Site of kaniya bridge

a year ago

on Saturday, August 10th 2024, 10:49:55 am
<span class="4">Picture Id:51782</span>
PWD Uttarakahnd
Photo (ID 51782) from Site Received
Uploader : Uma Shanker Kukreti, Additional Assistant Engineer Civil ,CD Ramnagar
Landmark : Hathidangar kaniya nala
Remark : Site of Bridge

a year ago

on Wednesday, October 16th 2024, 8:18:43 am
<span class="4">Picture Id:57123</span>
PWD Uttarakahnd
Photo (ID 57123) from Site Received
Uploader : Manoj Kumar Jain, Assistant Engineer Civil ,CD Ramnagar
Landmark : Kania Nala bridge
Remark : Layout of bridge

10 months ago

on Monday, December 2nd 2024, 6:30:00 pm
17.99%
Financial Progress

1st Expenditure
of ₹ 5015472 (50.15 Lacs ) done.
Cummulative ₹ 50.15Lacs ( against 278.78Lacs )

9 months ago

on Monday, December 16th 2024, 8:59:19 am
<span class="4">Picture Id:61238</span>
PWD Uttarakahnd
Photo (ID 61238) from Site Received
Uploader : Manoj Kumar Jain, Assistant Engineer Civil ,CD Ramnagar
Landmark : Kania Nala
Remark : Pile foundation work in progress

9 months ago

on Monday, December 16th 2024, 6:30:00 pm
8%

Physical Progress
Physical Progress Reported at 1st time

9 months ago

on Tuesday, December 17th 2024, 8:33:51 am
<span class="4">Picture Id:61322</span>
PWD Uttarakahnd
Photo (ID 61322) from Site Received
Uploader : Manoj Kumar Jain, Assistant Engineer Civil ,CD Ramnagar
Landmark : Kania Nala bridge
Remark : S.E.Sir Inspection of Kania Nala bridge

6 months ago

on Wednesday, March 19th 2025, 6:30:00 pm
37.10%
Financial Progress

2nd Expenditure
of ₹ 5328307 (53.28 Lacs ) done.
Cummulative ₹ 103.44Lacs ( against 278.78Lacs )

6 months ago

on Friday, March 21st 2025, 6:30:00 pm
37.56%
Financial Progress

4th Expenditure
of ₹ 115354 (1.15 Lacs ) done.
Cummulative ₹ 104.72Lacs ( against 278.78Lacs )

6 months ago

on Friday, March 21st 2025, 6:30:00 pm
37.15%
Financial Progress

3rd Expenditure
of ₹ 12411 (0.12 Lacs ) done.
Cummulative ₹ 103.56Lacs ( against 278.78Lacs )

6 months ago

on Tuesday, April 1st 2025, 6:30:00 pm
45%

Physical Progress
Physical Progress Reported at 2nd time

6 months ago

on Tuesday, April 1st 2025, 6:30:00 pm
37.56%
Financial Progress

5th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 104.72Lacs ( against 278.78Lacs )

5 months ago

on Sunday, April 27th 2025, 4:51:26 am
<span class="4">Picture Id:68395</span>
PWD Uttarakahnd
Photo (ID 68395) from Site Received
Uploader : Uma Shanker Kukreti, Additional Assistant Engineer Civil ,CD Ramnagar
Landmark : 30meter span steel girder bridge at kaniya nala
Remark : Concreting work in progress

4 months ago

on Wednesday, May 28th 2025, 6:30:00 pm
46.32%
Financial Progress

7th Expenditure
of ₹ 2441552 (24.42 Lacs ) done.
Cummulative ₹ 129.13Lacs ( against 278.78Lacs )

4 months ago

on Wednesday, May 28th 2025, 6:30:00 pm
37.56%
Financial Progress

6th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 104.72Lacs ( against 278.78Lacs )

3 months ago

on Thursday, June 26th 2025, 6:30:00 pm
50.91%
Financial Progress

8th Expenditure
of ₹ 1278270 (12.78 Lacs ) done.
Cummulative ₹ 141.91Lacs ( against 278.78Lacs )

3 months ago

on Monday, June 30th 2025, 6:30:00 pm
60%

Physical Progress
Physical Progress Reported at 3rd time

2 months ago

on Sunday, July 20th 2025, 6:30:00 pm
59.91%
Financial Progress

9th Expenditure
of ₹ 2508975 (25.09 Lacs ) done.
Cummulative ₹ 167.00Lacs ( against 278.78Lacs )

a month ago

on Monday, August 4th 2025, 6:30:00 pm
65%

Physical Progress
Physical Progress Reported at 4th time

17 days ago

on Monday, September 1st 2025, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 5th time