Refresh data
Refresh data

4 years ago

on Friday, December 10th 2021, 6:30:00 pm
Work Sanctioned
राज्य याजना के अन्तर्गत जनपद पौडी गढवाल के विधानसभा क्षेत्र चैबट्टाखाल विकासखण्ड एकेश्वर में सुन्ना हलाई मल्ली हलाई तल्ली मोटर मार्ग का निर्माण कार्य। (द्वितीय चरण स्टेज-।)

2 years ago

on Wednesday, September 27th 2023, 6:30:00 pm
0.64%
Financial Progress

1st Expenditure
of ₹ 66752 (0.67 Lacs ) done.
Cummulative ₹ 0.67Lacs ( against 104.43Lacs )

2 years ago

on Sunday, December 17th 2023, 6:30:00 pm
16.04%
Financial Progress

3rd Expenditure
of ₹ 896760 (8.97 Lacs ) done.
Cummulative ₹ 16.75Lacs ( against 104.43Lacs )

2 years ago

on Sunday, December 17th 2023, 6:30:00 pm
7.45%
Financial Progress

2nd Expenditure
of ₹ 711580 (7.12 Lacs ) done.
Cummulative ₹ 7.78Lacs ( against 104.43Lacs )

2 years ago

on Wednesday, December 27th 2023, 6:30:00 pm
16.12%
Financial Progress

4th Expenditure
of ₹ 7817 (0.08 Lacs ) done.
Cummulative ₹ 16.83Lacs ( against 104.43Lacs )

2 years ago

on Wednesday, December 27th 2023, 6:30:00 pm
16.13%
Financial Progress

5th Expenditure
of ₹ 1911 (0.02 Lacs ) done.
Cummulative ₹ 16.85Lacs ( against 104.43Lacs )

2 years ago

on Sunday, January 7th 2024, 6:30:00 pm
50%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Thursday, February 15th 2024, 6:30:00 pm
20.05%
Financial Progress

6th Expenditure
of ₹ 408696 (4.09 Lacs ) done.
Cummulative ₹ 20.94Lacs ( against 104.43Lacs )

2 years ago

on Thursday, February 15th 2024, 6:30:00 pm
25.69%
Financial Progress

7th Expenditure
of ₹ 589434 (5.89 Lacs ) done.
Cummulative ₹ 26.83Lacs ( against 104.43Lacs )

2 years ago

on Wednesday, March 20th 2024, 6:30:00 pm
27.08%
Financial Progress

8th Expenditure
of ₹ 145285 (1.45 Lacs ) done.
Cummulative ₹ 28.28Lacs ( against 104.43Lacs )

2 years ago

on Wednesday, March 20th 2024, 6:30:00 pm
29.42%
Financial Progress

9th Expenditure
of ₹ 243927 (2.44 Lacs ) done.
Cummulative ₹ 30.72Lacs ( against 104.43Lacs )

2 years ago

on Monday, March 25th 2024, 6:30:00 pm
34.93%
Financial Progress

10th Expenditure
of ₹ 575680 (5.76 Lacs ) done.
Cummulative ₹ 36.48Lacs ( against 104.43Lacs )

2 years ago

on Monday, March 25th 2024, 6:30:00 pm
38.25%
Financial Progress

11th Expenditure
of ₹ 346752 (3.47 Lacs ) done.
Cummulative ₹ 39.95Lacs ( against 104.43Lacs )

2 years ago

on Tuesday, May 14th 2024, 6:30:00 pm
46.48%
Financial Progress

12th Expenditure
of ₹ 859600 (8.60 Lacs ) done.
Cummulative ₹ 48.54Lacs ( against 104.43Lacs )

a year ago

on Sunday, June 2nd 2024, 6:30:00 pm
46.67%
Financial Progress

13th Expenditure
of ₹ 19612 (0.20 Lacs ) done.
Cummulative ₹ 48.74Lacs ( against 104.43Lacs )

a year ago

on Monday, June 17th 2024, 6:30:00 pm
48.26%
Financial Progress

14th Expenditure
of ₹ 165732 (1.66 Lacs ) done.
Cummulative ₹ 50.40Lacs ( against 104.43Lacs )

a year ago

on Thursday, June 27th 2024, 6:30:00 pm
52.70%
Financial Progress

15th Expenditure
of ₹ 463960 (4.64 Lacs ) done.
Cummulative ₹ 55.03Lacs ( against 104.43Lacs )

a year ago

on Friday, June 28th 2024, 6:30:00 pm
56.51%
Financial Progress

16th Expenditure
of ₹ 397622 (3.98 Lacs ) done.
Cummulative ₹ 59.01Lacs ( against 104.43Lacs )

a year ago

on Friday, August 2nd 2024, 6:30:00 pm
56.66%
Financial Progress

17th Expenditure
of ₹ 15790 (0.16 Lacs ) done.
Cummulative ₹ 59.17Lacs ( against 104.43Lacs )

a year ago

on Thursday, August 22nd 2024, 6:30:00 pm
56.90%
Financial Progress

18th Expenditure
of ₹ 24933 (0.25 Lacs ) done.
Cummulative ₹ 59.42Lacs ( against 104.43Lacs )

a year ago

on Friday, September 6th 2024, 6:30:00 pm
65%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Monday, November 4th 2024, 6:30:00 pm
57.81%
Financial Progress

19th Expenditure
of ₹ 95580 (0.96 Lacs ) done.
Cummulative ₹ 60.37Lacs ( against 104.43Lacs )

a year ago

on Friday, December 6th 2024, 6:30:00 pm
58.11%
Financial Progress

20th Expenditure
of ₹ 31128 (0.31 Lacs ) done.
Cummulative ₹ 60.69Lacs ( against 104.43Lacs )

a year ago

on Sunday, December 29th 2024, 6:30:00 pm
64.64%
Financial Progress

21st Expenditure
of ₹ 682080 (6.82 Lacs ) done.
Cummulative ₹ 67.51Lacs ( against 104.43Lacs )

10 months ago

on Tuesday, January 28th 2025, 6:30:00 pm
74.94%
Financial Progress

23rd Expenditure
of ₹ 572064 (5.72 Lacs ) done.
Cummulative ₹ 78.26Lacs ( against 104.43Lacs )

10 months ago

on Tuesday, January 28th 2025, 6:30:00 pm
69.47%
Financial Progress

22nd Expenditure
of ₹ 503624 (5.04 Lacs ) done.
Cummulative ₹ 72.54Lacs ( against 104.43Lacs )

9 months ago

on Wednesday, February 5th 2025, 6:30:00 pm
88.60%
Financial Progress

25th Expenditure
of ₹ 400250 (4.00 Lacs ) done.
Cummulative ₹ 92.53Lacs ( against 104.43Lacs )

9 months ago

on Wednesday, February 5th 2025, 6:30:00 pm
84.77%
Financial Progress

24th Expenditure
of ₹ 1026168 (10.26 Lacs ) done.
Cummulative ₹ 88.52Lacs ( against 104.43Lacs )

9 months ago

on Tuesday, February 18th 2025, 6:30:00 pm
89.52%
Financial Progress

27th Expenditure
of ₹ 13399 (0.13 Lacs ) done.
Cummulative ₹ 93.49Lacs ( against 104.43Lacs )

9 months ago

on Tuesday, February 18th 2025, 6:30:00 pm
89.39%
Financial Progress

26th Expenditure
of ₹ 82480 (0.82 Lacs ) done.
Cummulative ₹ 93.35Lacs ( against 104.43Lacs )

9 months ago

on Thursday, February 20th 2025, 6:30:00 pm
92.49%
Financial Progress

28th Expenditure
of ₹ 310204 (3.10 Lacs ) done.
Cummulative ₹ 96.59Lacs ( against 104.43Lacs )

9 months ago

on Sunday, February 23rd 2025, 6:30:00 pm
95.46%
Financial Progress

29th Expenditure
of ₹ 310204 (3.10 Lacs ) done.
Cummulative ₹ 99.69Lacs ( against 104.43Lacs )

8 months ago

on Monday, March 10th 2025, 6:30:00 pm
100.03%
Financial Progress

30th Expenditure
of ₹ 476720 (4.77 Lacs ) done.
Cummulative ₹ 104.46Lacs ( against 104.43Lacs )

8 months ago

on Wednesday, March 19th 2025, 6:30:00 pm
100.58%
Financial Progress

31st Expenditure
of ₹ 57832 (0.58 Lacs ) done.
Cummulative ₹ 105.04Lacs ( against 104.43Lacs )

8 months ago

on Thursday, March 20th 2025, 6:30:00 pm
91.15%
Financial Progress

32nd Expenditure
of ₹ -985080 (-9.85 Lacs ) done.
Cummulative ₹ 95.18Lacs ( against 104.43Lacs )

6 months ago

on Sunday, May 4th 2025, 6:30:00 pm
94.76%
Financial Progress

33rd Expenditure
of ₹ 377584 (3.78 Lacs ) done.
Cummulative ₹ 98.96Lacs ( against 104.43Lacs )

6 months ago

on Friday, May 30th 2025, 6:30:00 pm
96.98%
Financial Progress

34th Expenditure
of ₹ 231886 (2.32 Lacs ) done.
Cummulative ₹ 101.28Lacs ( against 104.43Lacs )

3 months ago

on Tuesday, August 26th 2025, 6:30:00 pm
100.23%
Financial Progress

35th Expenditure
of ₹ 339346 (3.39 Lacs ) done.
Cummulative ₹ 104.67Lacs ( against 104.43Lacs )

2 months ago

on Monday, September 29th 2025, 6:30:00 pm
99.89%
Financial Progress

36th Expenditure
of ₹ -36000 (-0.36 Lacs ) done.
Cummulative ₹ 104.31Lacs ( against 104.43Lacs )

a month ago

on Saturday, October 4th 2025, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 3rd time

4 days ago

on Monday, November 10th 2025, 6:30:00 pm
99.97%
Financial Progress

37th Expenditure
of ₹ 8050 (0.08 Lacs ) done.
Cummulative ₹ 104.39Lacs ( against 104.43Lacs )