Refresh data
on Tuesday, October 24th 2023, 6:30:00 pm
Work Sanctioned
मा0 मुख्य मंत्री घोषणा सं0 269/2022 राज्य योजना के अन्तर्गत जनपद पौडी गढवाल के विधानसभा क्षेत्र श्रीनगर के विकासखण्ड थैलीसैण में मैली मरखोला डाण्डा मरखोला मोटर मार्ग के सुदृडीकरण एवं डामरीकरण कार्य।
on Thursday, December 28th 2023, 6:55:52 am
Technical Sanction
of ₹ 218.65 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS VIDE SE Letter No 9055/1155yata-12/2023
on Wednesday, May 1st 2024, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, May 15th 2024, 6:30:00 pm
35%
Physical Progress
Physical Progress Reported at 2nd time
on Sunday, June 23rd 2024, 6:30:00 pm
0.23%
Financial Progress
1st Expenditure
of ₹ 52779 (0.53 Lacs ) done.
Cummulative ₹ 0.53Lacs ( against 226.48Lacs )
on Wednesday, June 26th 2024, 9:48:43 am
PWD UttarakahndPhoto (ID 47130) from Site Received
Uploader : Ashok Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : Maili Markhola Danda Markhola km 1 near maili
Remark : State Sector work in progress 1.0 meter span pulyia construction
on Friday, June 28th 2024, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 3rd time
on Friday, August 30th 2024, 6:30:00 pm
0.43%
Financial Progress
2nd Expenditure
of ₹ 45568 (0.46 Lacs ) done.
Cummulative ₹ 0.98Lacs ( against 226.48Lacs )
on Thursday, September 5th 2024, 8:44:53 am
PWD UttarakahndPhoto (ID 52501) from Site Received
Uploader : Ashok Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : Km 2,chainge 1.425
Remark : Village Markhola, km2
on Thursday, September 5th 2024, 8:53:16 am
PWD UttarakahndPhoto (ID 52502) from Site Received
Uploader : Ashok Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : Km 2, chainage 1.575
Remark : Km 2, village Baanjkoat
on Thursday, September 5th 2024, 8:57:55 am
PWD UttarakahndPhoto (ID 52503) from Site Received
Uploader : Ashok Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : Km 2, chainage 1.500
Remark : 1.00 mtr span supper
on Friday, September 6th 2024, 6:30:00 pm
30%
Physical Progress
Physical Progress Reported at 4th time
on Thursday, September 19th 2024, 6:30:00 pm
6.37%
Financial Progress
3rd Expenditure
of ₹ 1344399 (13.44 Lacs ) done.
Cummulative ₹ 14.43Lacs ( against 226.48Lacs )
on Thursday, September 26th 2024, 6:30:00 pm
12.92%
Financial Progress
4th Expenditure
of ₹ 1483423 (14.83 Lacs ) done.
Cummulative ₹ 29.26Lacs ( against 226.48Lacs )
on Monday, October 7th 2024, 6:00:35 am
PWD UttarakahndPhoto (ID 54275) from Site Received
Uploader : Ashok Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : KM 1,HM (0-2)
Remark : Soiling work at km 1,Danda Markhola rd
on Monday, October 21st 2024, 6:30:00 pm
26.55%
Financial Progress
5th Expenditure
of ₹ 3085831 (30.86 Lacs ) done.
Cummulative ₹ 60.12Lacs ( against 226.48Lacs )
on Wednesday, October 23rd 2024, 6:30:00 pm
55%
Physical Progress
Physical Progress Reported at 5th time
on Sunday, December 29th 2024, 6:30:00 pm
34.55%
Financial Progress
6th Expenditure
of ₹ 1811757 (18.12 Lacs ) done.
Cummulative ₹ 78.24Lacs ( against 226.48Lacs )
on Tuesday, January 28th 2025, 6:30:00 pm
53.98%
Financial Progress
7th Expenditure
of ₹ 4401630 (44.02 Lacs ) done.
Cummulative ₹ 122.25Lacs ( against 226.48Lacs )
on Sunday, March 2nd 2025, 6:30:00 pm
60.69%
Financial Progress
8th Expenditure
of ₹ 1520517 (15.21 Lacs ) done.
Cummulative ₹ 137.46Lacs ( against 226.48Lacs )
on Sunday, March 16th 2025, 6:30:00 pm
60.73%
Financial Progress
9th Expenditure
of ₹ 8789 (0.09 Lacs ) done.
Cummulative ₹ 137.55Lacs ( against 226.48Lacs )
on Sunday, March 23rd 2025, 6:30:00 pm
66.15%
Financial Progress
11th Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 149.82Lacs ( against 226.48Lacs )
on Sunday, March 23rd 2025, 6:30:00 pm
66.11%
Financial Progress
10th Expenditure
of ₹ 1217420 (12.17 Lacs ) done.
Cummulative ₹ 149.72Lacs ( against 226.48Lacs )
on Tuesday, April 1st 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 6th time
on Friday, May 30th 2025, 6:30:00 pm
85.18%
Financial Progress
12th Expenditure
of ₹ 4309018 (43.09 Lacs ) done.
Cummulative ₹ 192.91Lacs ( against 226.48Lacs )
on Tuesday, August 26th 2025, 6:30:00 pm
87.91%
Financial Progress
13th Expenditure
of ₹ 617764 (6.18 Lacs ) done.
Cummulative ₹ 199.09Lacs ( against 226.48Lacs )
on Friday, August 29th 2025, 6:30:00 pm
88.06%
Financial Progress
15th Expenditure
of ₹ 5310 (0.05 Lacs ) done.
Cummulative ₹ 199.45Lacs ( against 226.48Lacs )
on Friday, August 29th 2025, 6:30:00 pm
88.04%
Financial Progress
14th Expenditure
of ₹ 30680 (0.31 Lacs ) done.
Cummulative ₹ 199.40Lacs ( against 226.48Lacs )