2 years ago

on Tuesday, October 24th 2023, 6:30:00 pm
Work Sanctioned
मा0 मुख्य मंत्री घोषणा सं0 269/2022 राज्य योजना के अन्तर्गत जनपद पौडी गढवाल के विधानसभा क्षेत्र श्रीनगर के विकासखण्ड थैलीसैण में मैली मरखोला डाण्डा मरखोला मोटर मार्ग के सुदृडीकरण एवं डामरीकरण कार्य।

2 years ago

on Thursday, December 28th 2023, 6:55:52 am

Technical Sanction
of ₹ 218.65 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS VIDE SE Letter No 9055/1155yata-12/2023

2 years ago

on Wednesday, May 1st 2024, 6:30:00 pm
20%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Wednesday, May 15th 2024, 6:30:00 pm
35%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Sunday, June 23rd 2024, 6:30:00 pm
0.23%
Financial Progress

1st Expenditure
of ₹ 52779 (0.53 Lacs ) done.
Cummulative ₹ 0.53Lacs ( against 226.48Lacs )

a year ago

on Wednesday, June 26th 2024, 9:48:43 am
<span class="4">Picture Id:47130</span>
PWD Uttarakahnd
Photo (ID 47130) from Site Received
Uploader : Ashok Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : Maili Markhola Danda Markhola km 1 near maili
Remark : State Sector work in progress 1.0 meter span pulyia construction

a year ago

on Friday, June 28th 2024, 6:30:00 pm
20%

Physical Progress
Physical Progress Reported at 3rd time

a year ago

on Friday, August 30th 2024, 6:30:00 pm
0.43%
Financial Progress

2nd Expenditure
of ₹ 45568 (0.46 Lacs ) done.
Cummulative ₹ 0.98Lacs ( against 226.48Lacs )

a year ago

on Thursday, September 5th 2024, 8:44:53 am
<span class="4">Picture Id:52501</span>
PWD Uttarakahnd
Photo (ID 52501) from Site Received
Uploader : Ashok Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : Km 2,chainge 1.425
Remark : Village Markhola, km2

a year ago

on Thursday, September 5th 2024, 8:53:16 am
<span class="4">Picture Id:52502</span>
PWD Uttarakahnd
Photo (ID 52502) from Site Received
Uploader : Ashok Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : Km 2, chainage 1.575
Remark : Km 2, village Baanjkoat

a year ago

on Thursday, September 5th 2024, 8:57:55 am
<span class="4">Picture Id:52503</span>
PWD Uttarakahnd
Photo (ID 52503) from Site Received
Uploader : Ashok Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : Km 2, chainage 1.500
Remark : 1.00 mtr span supper

a year ago

on Friday, September 6th 2024, 6:30:00 pm
30%

Physical Progress
Physical Progress Reported at 4th time

a year ago

on Thursday, September 19th 2024, 6:30:00 pm
6.37%
Financial Progress

3rd Expenditure
of ₹ 1344399 (13.44 Lacs ) done.
Cummulative ₹ 14.43Lacs ( against 226.48Lacs )

a year ago

on Thursday, September 26th 2024, 6:30:00 pm
12.92%
Financial Progress

4th Expenditure
of ₹ 1483423 (14.83 Lacs ) done.
Cummulative ₹ 29.26Lacs ( against 226.48Lacs )

a year ago

on Monday, October 7th 2024, 6:00:35 am
<span class="4">Picture Id:54275</span>
PWD Uttarakahnd
Photo (ID 54275) from Site Received
Uploader : Ashok Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : KM 1,HM (0-2)
Remark : Soiling work at km 1,Danda Markhola rd

a year ago

on Monday, October 21st 2024, 6:30:00 pm
26.55%
Financial Progress

5th Expenditure
of ₹ 3085831 (30.86 Lacs ) done.
Cummulative ₹ 60.12Lacs ( against 226.48Lacs )

a year ago

on Wednesday, October 23rd 2024, 6:30:00 pm
55%

Physical Progress
Physical Progress Reported at 5th time

a year ago

on Sunday, December 29th 2024, 6:30:00 pm
34.55%
Financial Progress

6th Expenditure
of ₹ 1811757 (18.12 Lacs ) done.
Cummulative ₹ 78.24Lacs ( against 226.48Lacs )

10 months ago

on Tuesday, January 28th 2025, 6:30:00 pm
53.98%
Financial Progress

7th Expenditure
of ₹ 4401630 (44.02 Lacs ) done.
Cummulative ₹ 122.25Lacs ( against 226.48Lacs )

8 months ago

on Sunday, March 2nd 2025, 6:30:00 pm
60.69%
Financial Progress

8th Expenditure
of ₹ 1520517 (15.21 Lacs ) done.
Cummulative ₹ 137.46Lacs ( against 226.48Lacs )

8 months ago

on Sunday, March 16th 2025, 6:30:00 pm
60.73%
Financial Progress

9th Expenditure
of ₹ 8789 (0.09 Lacs ) done.
Cummulative ₹ 137.55Lacs ( against 226.48Lacs )

8 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
66.15%
Financial Progress

11th Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 149.82Lacs ( against 226.48Lacs )

8 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
66.11%
Financial Progress

10th Expenditure
of ₹ 1217420 (12.17 Lacs ) done.
Cummulative ₹ 149.72Lacs ( against 226.48Lacs )

7 months ago

on Tuesday, April 1st 2025, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 6th time

6 months ago

on Friday, May 30th 2025, 6:30:00 pm
85.18%
Financial Progress

12th Expenditure
of ₹ 4309018 (43.09 Lacs ) done.
Cummulative ₹ 192.91Lacs ( against 226.48Lacs )

3 months ago

on Tuesday, August 26th 2025, 6:30:00 pm
87.91%
Financial Progress

13th Expenditure
of ₹ 617764 (6.18 Lacs ) done.
Cummulative ₹ 199.09Lacs ( against 226.48Lacs )

3 months ago

on Friday, August 29th 2025, 6:30:00 pm
88.06%
Financial Progress

15th Expenditure
of ₹ 5310 (0.05 Lacs ) done.
Cummulative ₹ 199.45Lacs ( against 226.48Lacs )

3 months ago

on Friday, August 29th 2025, 6:30:00 pm
88.04%
Financial Progress

14th Expenditure
of ₹ 30680 (0.31 Lacs ) done.
Cummulative ₹ 199.40Lacs ( against 226.48Lacs )