Work Sanctioned
जनपद पौडी गढवाल के विधानसभा क्षेत्र श्रीनगर के विकासखण्ड थैलीसैण के अन्तर्गत पी0एम0जी0एस0वाई0 से हस्तगत कुचोली से कठूयूड मोटर मार्ग के वन टाइम मेन्टनैस का कार्य।
on Thursday, February 29th 2024, 11:40:57 am
Technical Sanction
of ₹ 156.78 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS VIDE EE Letter No 1292/1530Yata-12/2023
on Wednesday, May 1st 2024, 6:30:00 pm
30%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, June 26th 2024, 6:23:43 am
PWD UttarakahndPhoto (ID 46792) from Site Received
Uploader : Ashok Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : KM 2 ,Kucholi to Kathuar road OTM PMGSY
Remark : Work in progress
on Wednesday, June 26th 2024, 6:30:00 pm
25%
Physical Progress
Physical Progress Reported at 2nd time
on Friday, June 28th 2024, 6:30:00 pm
15%
Physical Progress
Physical Progress Reported at 3rd time
on Sunday, August 25th 2024, 6:30:00 pm
0.00%
Financial Progress
1st Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.00Lacs ( against 156.78Lacs )
on Wednesday, August 28th 2024, 6:30:00 pm
10.29%
Financial Progress
2nd Expenditure
of ₹ 1613836 (16.14 Lacs ) done.
Cummulative ₹ 16.14Lacs ( against 156.78Lacs )
on Wednesday, September 11th 2024, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 4th time
on Friday, October 25th 2024, 6:30:00 pm
30%
Physical Progress
Physical Progress Reported at 5th time
on Thursday, December 12th 2024, 6:30:00 pm
45%
Physical Progress
Physical Progress Reported at 6th time
on Monday, February 3rd 2025, 6:30:00 pm
75%
Physical Progress
Physical Progress Reported at 7th time
on Monday, April 21st 2025, 6:30:00 pm
45%
Physical Progress
Physical Progress Reported at 8th time
on Monday, May 19th 2025, 6:30:00 pm
12.49%
Financial Progress
3rd Expenditure
of ₹ 344000 (3.44 Lacs ) done.
Cummulative ₹ 19.58Lacs ( against 156.78Lacs )
on Friday, May 30th 2025, 6:30:00 pm
27.97%
Financial Progress
4th Expenditure
of ₹ 2427174 (24.27 Lacs ) done.
Cummulative ₹ 43.85Lacs ( against 156.78Lacs )
on Friday, June 20th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 9th time
on Wednesday, June 25th 2025, 6:30:00 pm
62.53%
Financial Progress
5th Expenditure
of ₹ 5418581 (54.19 Lacs ) done.
Cummulative ₹ 98.04Lacs ( against 156.78Lacs )
on Friday, August 29th 2025, 6:30:00 pm
63.16%
Financial Progress
6th Expenditure
of ₹ 99120 (0.99 Lacs ) done.
Cummulative ₹ 99.03Lacs ( against 156.78Lacs )
on Friday, August 29th 2025, 6:30:00 pm
63.51%
Financial Progress
7th Expenditure
of ₹ 54027 (0.54 Lacs ) done.
Cummulative ₹ 99.57Lacs ( against 156.78Lacs )