Work Sanctioned
मा0 मुख्यमंत्री घोषणा संख्या 269/2022 के अन्तर्गत जनपद पौडी गढवाल के विधानसभा क्षेत्र श्रीनगर के विकासखण्ड पाबौ में पाबौ चम्पेश्वर से सुन्द्रियू मोटर मार्ग का डामरीकरण एवं सुदृडीकरण का कार्य।

2 years ago

on Thursday, March 14th 2024, 6:30:00 pm

Technical Sanction
of ₹ 100.18 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 452/TS

a year ago

on Tuesday, June 11th 2024, 6:30:00 pm
0.00%
Financial Progress

1st Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.00Lacs ( against 100.18Lacs )

a year ago

on Thursday, June 27th 2024, 7:23:13 am
<span class="4">Picture Id:47685</span>
PWD Uttarakahnd
Photo (ID 47685) from Site Received
Uploader : Anil Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : Km 1 H. M 0-2
Remark : Pabou champaswar to sundrayo motor road km 1 Defect cutting work under state sector

a year ago

on Thursday, June 27th 2024, 6:30:00 pm
7.04%
Financial Progress

2nd Expenditure
of ₹ 704846 (7.05 Lacs ) done.
Cummulative ₹ 7.05Lacs ( against 100.18Lacs )

a year ago

on Tuesday, July 23rd 2024, 6:30:00 pm
7.04%
Financial Progress

3rd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 7.05Lacs ( against 100.18Lacs )

a year ago

on Friday, August 2nd 2024, 6:30:00 pm
11.72%
Financial Progress

4th Expenditure
of ₹ 468918 (4.69 Lacs ) done.
Cummulative ₹ 11.74Lacs ( against 100.18Lacs )

a year ago

on Wednesday, October 23rd 2024, 6:30:00 pm
15%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Monday, October 28th 2024, 6:30:00 pm
18.40%
Financial Progress

5th Expenditure
of ₹ 669864 (6.70 Lacs ) done.
Cummulative ₹ 18.44Lacs ( against 100.18Lacs )

a year ago

on Monday, November 4th 2024, 6:30:00 pm
18.96%
Financial Progress

6th Expenditure
of ₹ 56138 (0.56 Lacs ) done.
Cummulative ₹ 19.00Lacs ( against 100.18Lacs )

a year ago

on Thursday, December 19th 2024, 6:30:00 pm
19.62%
Financial Progress

7th Expenditure
of ₹ 65588 (0.66 Lacs ) done.
Cummulative ₹ 19.65Lacs ( against 100.18Lacs )

a year ago

on Sunday, December 22nd 2024, 6:30:00 pm
20.26%
Financial Progress

8th Expenditure
of ₹ 64000 (0.64 Lacs ) done.
Cummulative ₹ 20.29Lacs ( against 100.18Lacs )

a year ago

on Sunday, December 29th 2024, 6:30:00 pm
28.40%
Financial Progress

9th Expenditure
of ₹ 815713 (8.16 Lacs ) done.
Cummulative ₹ 28.45Lacs ( against 100.18Lacs )

10 months ago

on Tuesday, January 28th 2025, 6:30:00 pm
40.77%
Financial Progress

10th Expenditure
of ₹ 1239186 (12.39 Lacs ) done.
Cummulative ₹ 40.84Lacs ( against 100.18Lacs )

8 months ago

on Tuesday, March 18th 2025, 6:30:00 pm
31.42%
Financial Progress

11th Expenditure
of ₹ -937041 (-9.37 Lacs ) done.
Cummulative ₹ 31.47Lacs ( against 100.18Lacs )

6 months ago

on Thursday, May 1st 2025, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 2nd time

6 months ago

on Sunday, May 4th 2025, 6:30:00 pm
58.20%
Financial Progress

12th Expenditure
of ₹ 2682974 (26.83 Lacs ) done.
Cummulative ₹ 58.30Lacs ( against 100.18Lacs )

6 months ago

on Monday, May 5th 2025, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 3rd time

6 months ago

on Thursday, May 29th 2025, 6:30:00 pm
66.48%
Financial Progress

13th Expenditure
of ₹ 829785 (8.30 Lacs ) done.
Cummulative ₹ 66.60Lacs ( against 100.18Lacs )

6 months ago

on Friday, May 30th 2025, 6:30:00 pm
70.73%
Financial Progress

15th Expenditure
of ₹ 98978 (0.99 Lacs ) done.
Cummulative ₹ 70.86Lacs ( against 100.18Lacs )

6 months ago

on Friday, May 30th 2025, 6:30:00 pm
69.74%
Financial Progress

14th Expenditure
of ₹ 326773 (3.27 Lacs ) done.
Cummulative ₹ 69.87Lacs ( against 100.18Lacs )

5 months ago

on Sunday, June 15th 2025, 6:30:00 pm
71.19%
Financial Progress

16th Expenditure
of ₹ 46090 (0.46 Lacs ) done.
Cummulative ₹ 71.32Lacs ( against 100.18Lacs )

5 months ago

on Wednesday, June 25th 2025, 6:30:00 pm
71.44%
Financial Progress

17th Expenditure
of ₹ 24717 (0.25 Lacs ) done.
Cummulative ₹ 71.57Lacs ( against 100.18Lacs )

2 months ago

on Thursday, September 25th 2025, 6:30:00 pm
75.74%
Financial Progress

18th Expenditure
of ₹ 431046 (4.31 Lacs ) done.
Cummulative ₹ 75.88Lacs ( against 100.18Lacs )

2 months ago

on Monday, September 29th 2025, 6:30:00 pm
72.94%
Financial Progress

19th Expenditure
of ₹ -280000 (-2.80 Lacs ) done.
Cummulative ₹ 73.08Lacs ( against 100.18Lacs )

a month ago

on Saturday, October 4th 2025, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 4th time

4 days ago

on Monday, November 10th 2025, 6:30:00 pm
73.43%
Financial Progress

20th Expenditure
of ₹ 49088 (0.49 Lacs ) done.
Cummulative ₹ 73.57Lacs ( against 100.18Lacs )