2 years ago

on Monday, March 11th 2024, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री घोषणा संख्या 269ध्2022 के अन्तर्गत जनपद पौडी गढवाल के विधानसभा क्षेत्र श्रीनगर के विकासखण्ड पाबौ में चोलोसैण पोखरी ढुमका मोटर मार्ग के डामरीकरण एवं सुदृडीकरण का कार्य।

2 years ago

on Thursday, March 14th 2024, 6:51:53 am

Technical Sanction
of ₹ 216.27 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS VIDE EE Letter No 429/TS

a year ago

on Wednesday, May 1st 2024, 6:30:00 pm
20%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Thursday, June 6th 2024, 6:30:00 pm
30%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Monday, June 17th 2024, 6:30:00 pm
0.00%
Financial Progress

1st Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.00Lacs ( against 225.42Lacs )

a year ago

on Wednesday, June 26th 2024, 12:06:45 pm
<span class="4">Picture Id:47292</span>
PWD Uttarakahnd
Photo (ID 47292) from Site Received
Uploader : Sanjay Kumar, Junior Engineer Civil ,CD Pabo
Landmark : Km 2 chainage 1/2-3
Remark : Clearing of slip

a year ago

on Wednesday, June 26th 2024, 12:14:02 pm
<span class="4">Picture Id:47300</span>
PWD Uttarakahnd
Photo (ID 47300) from Site Received
Uploader : Sanjay Kumar, Junior Engineer Civil ,CD Pabo
Landmark : Km 2 chainage 1/39-40
Remark : Collection of stones (G-1)

a year ago

on Wednesday, June 26th 2024, 12:18:16 pm
<span class="4">Picture Id:47302</span>
PWD Uttarakahnd
Photo (ID 47302) from Site Received
Uploader : Sanjay Kumar, Junior Engineer Civil ,CD Pabo
Landmark : Km 3 chainage 2/6-7
Remark : Collection of stones (G-1)

a year ago

on Thursday, June 27th 2024, 6:30:00 pm
6.61%
Financial Progress

2nd Expenditure
of ₹ 1489886 (14.90 Lacs ) done.
Cummulative ₹ 14.90Lacs ( against 225.42Lacs )

a year ago

on Tuesday, July 30th 2024, 6:30:00 pm
20.03%
Financial Progress

3rd Expenditure
of ₹ 3026000 (30.26 Lacs ) done.
Cummulative ₹ 45.16Lacs ( against 225.42Lacs )

a year ago

on Sunday, August 4th 2024, 6:30:00 pm
27.27%
Financial Progress

4th Expenditure
of ₹ 1631207 (16.31 Lacs ) done.
Cummulative ₹ 61.47Lacs ( against 225.42Lacs )

a year ago

on Monday, August 19th 2024, 6:30:00 pm
27.27%
Financial Progress

5th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 61.47Lacs ( against 225.42Lacs )

a year ago

on Wednesday, August 21st 2024, 6:30:00 pm
40.34%
Financial Progress

6th Expenditure
of ₹ 2946383 (29.46 Lacs ) done.
Cummulative ₹ 90.93Lacs ( against 225.42Lacs )

a year ago

on Thursday, August 29th 2024, 6:30:00 pm
35%

Physical Progress
Physical Progress Reported at 3rd time

a year ago

on Friday, August 30th 2024, 6:30:00 pm
44.92%
Financial Progress

7th Expenditure
of ₹ 1032524 (10.33 Lacs ) done.
Cummulative ₹ 101.26Lacs ( against 225.42Lacs )

a year ago

on Friday, September 6th 2024, 6:30:00 pm
40%

Physical Progress
Physical Progress Reported at 4th time

a year ago

on Wednesday, October 23rd 2024, 6:30:00 pm
50%

Physical Progress
Physical Progress Reported at 5th time

9 months ago

on Thursday, December 19th 2024, 6:30:00 pm
44.95%
Financial Progress

8th Expenditure
of ₹ 5583 (0.06 Lacs ) done.
Cummulative ₹ 101.32Lacs ( against 225.42Lacs )

9 months ago

on Sunday, December 22nd 2024, 6:30:00 pm
58.64%
Financial Progress

9th Expenditure
of ₹ 3086692 (30.87 Lacs ) done.
Cummulative ₹ 132.18Lacs ( against 225.42Lacs )

9 months ago

on Sunday, December 29th 2024, 6:30:00 pm
66.65%
Financial Progress

10th Expenditure
of ₹ 1805588 (18.06 Lacs ) done.
Cummulative ₹ 150.24Lacs ( against 225.42Lacs )

8 months ago

on Sunday, January 19th 2025, 6:30:00 pm
68.96%
Financial Progress

11th Expenditure
of ₹ 520795 (5.21 Lacs ) done.
Cummulative ₹ 155.45Lacs ( against 225.42Lacs )

8 months ago

on Tuesday, January 28th 2025, 6:30:00 pm
77.90%
Financial Progress

12th Expenditure
of ₹ 2015023 (20.15 Lacs ) done.
Cummulative ₹ 175.60Lacs ( against 225.42Lacs )

6 months ago

on Friday, March 14th 2025, 6:30:00 pm
82.45%
Financial Progress

13th Expenditure
of ₹ 1026351 (10.26 Lacs ) done.
Cummulative ₹ 185.86Lacs ( against 225.42Lacs )

6 months ago

on Tuesday, April 1st 2025, 6:30:00 pm
75%

Physical Progress
Physical Progress Reported at 6th time

5 months ago

on Thursday, May 1st 2025, 6:30:00 pm
95%

Physical Progress
Physical Progress Reported at 7th time

4 months ago

on Friday, May 30th 2025, 6:30:00 pm
89.75%
Financial Progress

14th Expenditure
of ₹ 1645027 (16.45 Lacs ) done.
Cummulative ₹ 202.31Lacs ( against 225.42Lacs )

3 months ago

on Sunday, June 29th 2025, 6:30:00 pm
90.96%
Financial Progress

15th Expenditure
of ₹ 273622 (2.74 Lacs ) done.
Cummulative ₹ 205.05Lacs ( against 225.42Lacs )

AI layer

AI Road
AI Bridge
10000 km
5000 mi
Unavailable