Work Sanctioned
मा0 मुख्यमंत्री घोषणा संख्या 269ध्2022 के अन्तर्गत जनपद पौडी गढवाल के विधानसभा क्षेत्र श्रीनगर के विकासखण्ड पाबौ में चोलोसैण पोखरी ढुमका मोटर मार्ग के डामरीकरण एवं सुदृडीकरण का कार्य।
on Thursday, March 14th 2024, 6:51:53 am
Technical Sanction
of ₹ 216.27 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS VIDE EE Letter No 429/TS
on Wednesday, May 1st 2024, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, June 6th 2024, 6:30:00 pm
30%
Physical Progress
Physical Progress Reported at 2nd time
on Monday, June 17th 2024, 6:30:00 pm
0.00%
Financial Progress
1st Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.00Lacs ( against 225.42Lacs )
on Wednesday, June 26th 2024, 12:06:45 pm
PWD UttarakahndPhoto (ID 47292) from Site Received
Uploader : Sanjay Kumar, Junior Engineer Civil ,CD Pabo
Landmark : Km 2 chainage 1/2-3
Remark : Clearing of slip
on Wednesday, June 26th 2024, 12:14:02 pm
PWD UttarakahndPhoto (ID 47300) from Site Received
Uploader : Sanjay Kumar, Junior Engineer Civil ,CD Pabo
Landmark : Km 2 chainage 1/39-40
Remark : Collection of stones (G-1)
on Wednesday, June 26th 2024, 12:18:16 pm
PWD UttarakahndPhoto (ID 47302) from Site Received
Uploader : Sanjay Kumar, Junior Engineer Civil ,CD Pabo
Landmark : Km 3 chainage 2/6-7
Remark : Collection of stones (G-1)
on Thursday, June 27th 2024, 6:30:00 pm
6.61%
Financial Progress
2nd Expenditure
of ₹ 1489886 (14.90 Lacs ) done.
Cummulative ₹ 14.90Lacs ( against 225.42Lacs )
on Tuesday, July 30th 2024, 6:30:00 pm
20.03%
Financial Progress
3rd Expenditure
of ₹ 3026000 (30.26 Lacs ) done.
Cummulative ₹ 45.16Lacs ( against 225.42Lacs )
on Sunday, August 4th 2024, 6:30:00 pm
27.27%
Financial Progress
4th Expenditure
of ₹ 1631207 (16.31 Lacs ) done.
Cummulative ₹ 61.47Lacs ( against 225.42Lacs )
on Monday, August 19th 2024, 6:30:00 pm
27.27%
Financial Progress
5th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 61.47Lacs ( against 225.42Lacs )
on Wednesday, August 21st 2024, 6:30:00 pm
40.34%
Financial Progress
6th Expenditure
of ₹ 2946383 (29.46 Lacs ) done.
Cummulative ₹ 90.93Lacs ( against 225.42Lacs )
on Thursday, August 29th 2024, 6:30:00 pm
35%
Physical Progress
Physical Progress Reported at 3rd time
on Friday, August 30th 2024, 6:30:00 pm
44.92%
Financial Progress
7th Expenditure
of ₹ 1032524 (10.33 Lacs ) done.
Cummulative ₹ 101.26Lacs ( against 225.42Lacs )
on Friday, September 6th 2024, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 4th time
on Wednesday, October 23rd 2024, 6:30:00 pm
50%
Physical Progress
Physical Progress Reported at 5th time
on Thursday, December 19th 2024, 6:30:00 pm
44.95%
Financial Progress
8th Expenditure
of ₹ 5583 (0.06 Lacs ) done.
Cummulative ₹ 101.32Lacs ( against 225.42Lacs )
on Sunday, December 22nd 2024, 6:30:00 pm
58.64%
Financial Progress
9th Expenditure
of ₹ 3086692 (30.87 Lacs ) done.
Cummulative ₹ 132.18Lacs ( against 225.42Lacs )
on Sunday, December 29th 2024, 6:30:00 pm
66.65%
Financial Progress
10th Expenditure
of ₹ 1805588 (18.06 Lacs ) done.
Cummulative ₹ 150.24Lacs ( against 225.42Lacs )
on Sunday, January 19th 2025, 6:30:00 pm
68.96%
Financial Progress
11th Expenditure
of ₹ 520795 (5.21 Lacs ) done.
Cummulative ₹ 155.45Lacs ( against 225.42Lacs )
on Tuesday, January 28th 2025, 6:30:00 pm
77.90%
Financial Progress
12th Expenditure
of ₹ 2015023 (20.15 Lacs ) done.
Cummulative ₹ 175.60Lacs ( against 225.42Lacs )
on Friday, March 14th 2025, 6:30:00 pm
82.45%
Financial Progress
13th Expenditure
of ₹ 1026351 (10.26 Lacs ) done.
Cummulative ₹ 185.86Lacs ( against 225.42Lacs )
on Tuesday, April 1st 2025, 6:30:00 pm
75%
Physical Progress
Physical Progress Reported at 6th time
on Thursday, May 1st 2025, 6:30:00 pm
95%
Physical Progress
Physical Progress Reported at 7th time
on Friday, May 30th 2025, 6:30:00 pm
89.75%
Financial Progress
14th Expenditure
of ₹ 1645027 (16.45 Lacs ) done.
Cummulative ₹ 202.31Lacs ( against 225.42Lacs )
on Sunday, June 29th 2025, 6:30:00 pm
90.96%
Financial Progress
15th Expenditure
of ₹ 273622 (2.74 Lacs ) done.
Cummulative ₹ 205.05Lacs ( against 225.42Lacs )