13 years ago

on Sunday, January 13th 2013, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री घोषणान्तर्गत जनपद चमोली के विधानसभा क्षेत्र कर्णप्रयाग तथा विकासखण्ड गैरसैण में खजूरखाल में निगलानी-तिमुलपानी-गौगनानी-दमदड़ तक मोटर मार्ग का निर्माण।

11 years ago

on Saturday, February 28th 2015, 6:30:00 pm
0.33%
Financial Progress

1st Expenditure
of ₹ 25000 (0.25 Lacs ) done.
Cummulative ₹ 0.25Lacs ( against 75.6Lacs )

10 years ago

on Tuesday, June 30th 2015, 6:30:00 pm
0.69%
Financial Progress

2nd Expenditure
of ₹ 26923 (0.27 Lacs ) done.
Cummulative ₹ 0.52Lacs ( against 75.6Lacs )

9 years ago

on Sunday, July 31st 2016, 6:30:00 pm
3.51%
Financial Progress

3rd Expenditure
of ₹ 213140 (2.13 Lacs ) done.
Cummulative ₹ 2.65Lacs ( against 75.6Lacs )

8 years ago

on Wednesday, February 28th 2018, 6:30:00 pm
7.86%
Financial Progress

4th Expenditure
of ₹ 329400 (3.29 Lacs ) done.
Cummulative ₹ 5.94Lacs ( against 75.6Lacs )

4 years ago

on Monday, November 22nd 2021, 6:30:00 pm
13.93%
Financial Progress

5th Expenditure
of ₹ 458793 (4.59 Lacs ) done.
Cummulative ₹ 10.53Lacs ( against 75.6Lacs )

4 years ago

on Thursday, December 2nd 2021, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Wednesday, October 23rd 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 2nd time

9 months ago

on Thursday, December 19th 2024, 6:30:00 pm
19.51%
Financial Progress

6th Expenditure
of ₹ 421520 (4.22 Lacs ) done.
Cummulative ₹ 14.75Lacs ( against 75.6Lacs )

7 months ago

on Monday, February 24th 2025, 6:30:00 pm
31.32%
Financial Progress

14th Expenditure
of ₹ 98000 (0.98 Lacs ) done.
Cummulative ₹ 23.68Lacs ( against 75.6Lacs )

7 months ago

on Monday, February 24th 2025, 6:30:00 pm
30.03%
Financial Progress

13th Expenditure
of ₹ 123200 (1.23 Lacs ) done.
Cummulative ₹ 22.70Lacs ( against 75.6Lacs )

7 months ago

on Monday, February 24th 2025, 6:30:00 pm
28.40%
Financial Progress

12th Expenditure
of ₹ 145600 (1.46 Lacs ) done.
Cummulative ₹ 21.47Lacs ( against 75.6Lacs )

7 months ago

on Monday, February 24th 2025, 6:30:00 pm
21.40%
Financial Progress

7th Expenditure
of ₹ 142800 (1.43 Lacs ) done.
Cummulative ₹ 16.18Lacs ( against 75.6Lacs )

7 months ago

on Monday, February 24th 2025, 6:30:00 pm
22.84%
Financial Progress

8th Expenditure
of ₹ 109200 (1.09 Lacs ) done.
Cummulative ₹ 17.27Lacs ( against 75.6Lacs )

7 months ago

on Monday, February 24th 2025, 6:30:00 pm
23.99%
Financial Progress

9th Expenditure
of ₹ 86800 (0.87 Lacs ) done.
Cummulative ₹ 18.14Lacs ( against 75.6Lacs )

7 months ago

on Monday, February 24th 2025, 6:30:00 pm
26.47%
Financial Progress

11th Expenditure
of ₹ 109200 (1.09 Lacs ) done.
Cummulative ₹ 20.01Lacs ( against 75.6Lacs )

7 months ago

on Monday, February 24th 2025, 6:30:00 pm
25.03%
Financial Progress

10th Expenditure
of ₹ 78400 (0.78 Lacs ) done.
Cummulative ₹ 18.92Lacs ( against 75.6Lacs )

7 months ago

on Tuesday, February 25th 2025, 6:30:00 pm
34.19%
Financial Progress

16th Expenditure
of ₹ 40260 (0.40 Lacs ) done.
Cummulative ₹ 25.85Lacs ( against 75.6Lacs )

7 months ago

on Tuesday, February 25th 2025, 6:30:00 pm
33.66%
Financial Progress

15th Expenditure
of ₹ 176400 (1.76 Lacs ) done.
Cummulative ₹ 25.44Lacs ( against 75.6Lacs )

7 months ago

on Thursday, February 27th 2025, 6:30:00 pm
34.19%
Financial Progress

17th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 25.85Lacs ( against 75.6Lacs )

6 months ago

on Monday, March 3rd 2025, 6:30:00 pm
35.30%
Financial Progress

18th Expenditure
of ₹ 84000 (0.84 Lacs ) done.
Cummulative ₹ 26.69Lacs ( against 75.6Lacs )

6 months ago

on Monday, March 3rd 2025, 6:30:00 pm
35.35%
Financial Progress

19th Expenditure
of ₹ 3560 (0.04 Lacs ) done.
Cummulative ₹ 26.72Lacs ( against 75.6Lacs )